Project Completion Certificate (Ground Water)
Scheme ID: 20011891 Name of Scheme: SAREJU No. of Villages: 2 No. of Habitation Covered: 12
Total Population Covered: 6150 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 14-Jun-2023 Actual Date of Completion (Capex): 26-Mar-2023
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 35.06M/ 112.78M SAREJU 27.677185 80.178797
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 1.400 M³ per Min /45Mtr SAREJU 27.677185 80.178797
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 400KL/ 18Mtr SAREJU 27.677028 80.178668
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 D.I. Pipe 200 0.0183
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6, Class PE-100 63 9.6877
2 HDPE Pipe PN-6, Class PE-100 75 8.553
3 HDPE Pipe PN-6, Class PE-100 90 5.999
4 HDPE Pipe PN-6, Class PE-100 110 1.356
5 HDPE Pipe PN-6, Class PE-100 125 1.197
6 HDPE Pipe PN-6, Class PE-100 140 0.408
7 HDPE Pipe PN-6, Class PE-100 160 1.066
8 HDPE Pipe PN-6, Class PE-100 200 1.406
HSC Connection
Sno. Total Nos.
1 842
Other Details
4.38
0.00
4.28
25-Jun-2023
24-Dec-2024