Project Completion Certificate (Ground Water)
Scheme ID: 20012290 Name of Scheme: GAJU-KACHAUNA No. of Villages: 1 No. of Habitation Covered: 9
Total Population Covered: 10420 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 26-Jul-2023 Actual Date of Completion (Capex): 06-Dec-2023
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 30M/ 115.01M GAJU 27.208209 80.365902
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 0.900 M³ per Min /45Mtr GAJU 27.208209 80.365902
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 300KL/ 18Mtr GAJU 27.208229 80.365934
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 D. I. Pipe 150 0.0215
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6, Class PE-100 63 11.5178
2 HDPE Pipe PN-6, Class PE-100 75 7.8058
3 HDPE Pipe PN-6, Class PE-100 90 4.2713
4 HDPE Pipe PN-6, Class PE-100 110 2.8533
5 HDPE Pipe PN-6, Class PE-100 125 2.6825
6 HDPE Pipe PN-6, Class PE-100 140 2.367
7 HDPE Pipe PN-6, Class PE-100 160 2.9532
8 HDPE Pipe PN-6, Class PE-100 180 0.3585
9 HDPE Pipe PN-6, Class PE-100 200 1.3827
HSC Connection
Sno. Total Nos.
1 1534
Other Details
5.78
0.00
5.66
05-Mar-2024
24-Dec-2024