Project Completion Certificate (Ground Water)
Scheme ID: 20012433 Name of Scheme: Sardapur No. of Villages: 3 No. of Habitation Covered: 3
Total Population Covered: 2530 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 26-Jul-2023 Actual Date of Completion (Capex): 20-Oct-2023
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 22.01M/ 95.87M Sardapur 27.384794 80.321282
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 0.6 M³ per Min /43Mtr Sardapur 27.384794 80.321282
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 175KL/ 12Mtr Sardapur 27.384683 80.321305
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 D. I. Pipe 150 0.02131
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6, Class PE-100 63 4.7401
2 HDPE Pipe PN-6, Class PE-100 75 3.7826
3 HDPE Pipe PN-6, Class PE-100 90 0.6167
4 HDPE Pipe PN-6, Class PE-100 110 4.022
5 HDPE Pipe PN-6, Class PE-100 140 0.241
6 HDPE Pipe PN-6, Class PE-100 160 0.047
HSC Connection
Sno. Total Nos.
1 331
Other Details
2.48
0.00
2.40
19-Jan-2024
25-Dec-2024