Project Completion Certificate (Ground Water)
Scheme ID: 20015090 Name of Scheme: Rao Bahadur No. of Villages: 1 No. of Habitation Covered: 3
Total Population Covered: 2460 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 26-Jul-2023 Actual Date of Completion (Capex): 20-Oct-2023
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 23M/ 114.8M Rao Bahadur 27.234175 80.273007
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 0.6 M³ per Min /45Mtr Rao Bahadur 27.234175 80.273007
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 175KL/ 16Mtr Rao Bahadur 27.260553 80.301218
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 D. I. Pipe 150 0.02582
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6, Class PE-100 63 4.1159
2 HDPE Pipe PN-6, Class PE-100 75 1.7194
3 HDPE Pipe PN-6, Class PE-100 90 0.5279
4 HDPE Pipe PN-6, Class PE-100 110 1.8628
5 HDPE Pipe PN-6, Class PE-100 125 0.0781
6 HDPE Pipe PN-6, Class PE-100 160 0.780
7 HDPE Pipe PN-6, Class PE-100 180 0.784
HSC Connection
Sno. Total Nos.
1 414
Other Details
2.48
0.00
2.40
19-Jan-2024
24-Dec-2024