| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20023889 | Name of Scheme: Khurrampur Dallu Gram Panchayat Water Supply | No. of Villages: 3 | No. of Habitation Covered: 3 |
| Total Population Covered: 2836 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 06-Jul-2023 | Actual Date of Completion (Capex): 19-May-2025 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tube-Well | 30.16/150.23 | Khurrampur Dallu | 29.408252 | 78.422389 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible Pump | 650/60 | Khurrampur Dallu | 29.408252 | 78.422389 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT-1 | 200/16 | Khurrampur Dallu | 29.408252 | 78.422389 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI - K7 | 150 | 0.039 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 6.4246 | |
| 2 | HDPE | 75 | 0.0988 | |
| 3 | HDPE | 90 | 0.0698 | |
| 4 | HDPE | 110 | 0.1308 | |
| 5 | HDPE | 125 | 0.0918 | |
| 6 | HDPE | 140 | 0.036 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 554 |