Project Completion Certificate (Ground Water)
Scheme ID: 20051436 Name of Scheme: MADARIPUR VILLAGE WATER SUPPLY SCHEME No. of Villages: 3 No. of Habitation Covered: 26
Total Population Covered: 3894 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 17-Dec-2023 Actual Date of Completion (Capex): 10-Jul-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 300 15.14m/77.11m MADARIPUR 26.058317 82.485828
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 15HP 755LPM/47m MADARIPUR 26.058317 82.485828
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 225KL/16M MADARIPUR 26.058405 82.485608
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI K-7 150 0.03555 Yes
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 90 3.029 Yes
2 HDPE 75 5.518 Yes
3 HDPE 63 11.998 Yes
4 HDPE 110 1.585 Yes
5 HDPE 140 0.735 Yes
6 HDPE 160 0.754 Yes
7 HDPE 180 1.168 Yes
8 HDPE 200 0.978 Yes
HSC Connection
Sno. Total Nos.
1 397
Other Details
3.08
3.08
2.98
10-Jul-2025
10-Jul-2025