| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 8359409 | Name of Scheme: Indapamau | No. of Villages: 1 | No. of Habitation Covered: 1 |
| Total Population Covered: 1920 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 08-May-2023 | Actual Date of Completion (Capex): 25-Feb-2023 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tube Well | 18.09 Mtr./111.46 Mtr. | Indapamau | 26.7656475* | 79.5448468* |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible | (27.4M3/Hr.)/58Mtr. | Indapamau | 26.7656475* | 79.5448468* |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 150/16 | Indapamau | 26.7658311* | 79.544692* |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | D.I. | 100 | .015 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 3.726 | |
| 2 | HDPE | 75 | .139 | |
| 3 | HDPE | 90 | 0.208 | |
| 4 | HDPE | 110 | .061 | |
| 5 | HDPE | 140 | .259 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 351 |