Project Completion Certificate (Ground Water)
Scheme ID: 8362909 Name of Scheme: KALYANPUR JAGOO No. of Villages: 1 No. of Habitation Covered: 3
Total Population Covered: 2255 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 12-Oct-2022 Actual Date of Completion (Capex): 05-May-2023
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tube Well 21.10 Mtr./62.80 Mtr. Kalyanpur Jagoo 26.737344* 79.515726*
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible (27.2M3/Hr.)/46Mtr. Kalyanpur Jagoo 26.737344* 79.515726*
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 150/16 Kalyanpur Jagoo 26.737437* 79.515663*
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 D.I. 100 .013
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 4.40
2 HDPE 75 .50
3 HDPE 90 .33
4 HDPE 110 1.26
5 HDPE 140 .07
HSC Connection
Sno. Total Nos.
1 374
Other Details
1.80
1.71
1.71
20-May-2023
20-Aug-2023