| S.No. | District | Agency | Scheme Id | Scheme Name | Phase | No.Of.Village | T/W Approved | T/W Completed | Total OHT | OHT Completed | Distribution Line Laying Approved(KM) | Distribution Line Laying Completed(KM) | Har Gar Jal Villages | HGJ Certified Villages | Handed Over Villages |
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Total | 6 | 6 | 6 | 4 | 4 | 44.09 | 104.54 | 6 | 4 | 0 | |||||
| 1 | Shamli | Gayatri Projects LTD | 1732401 | Bhutrada PWS | PHASE-2 | 1 | 1 | 1 | 0 | 0 | 16.76 | 17.00 | 1 | 1 | 0 |
| 2 | Shamli | JMC - Lakshmi (JV) | 8362284 | Badhupura & Gajipura GOV Water Supply Scheme | PHASE-2 | 2 | 1 | 1 | 1 | 1 | 5.28 | 65.69 | 2 | 2 | 0 |
| 3 | Shamli | Gayatri Projects LTD | 20021708 | Karaunda Hati Village Water Supply Scheme Reorgination | PHASE-2 | 1 | 2 | 2 | 1 | 1 | 10.21 | 10.21 | 1 | 1 | 0 |
| 4 | Shamli | JMC - Lakshmi (JV) | 20068395 | Kaserwakalan Village Water Supply Scheme | PHASE-2 | 1 | 1 | 1 | 1 | 1 | 9.86 | 9.95 | 1 | 0 | 0 |
| 5 | Shamli | JMC - Lakshmi (JV) | 20100744 | Saihata Village Water Supply Scheme | PHASE-2 | 1 | 1 | 1 | 1 | 1 | 1.98 | 1.69 | 1 | 0 | 0 |