Construction Schemes Disruptions



S.No. District Agency Scheme Village OHT Code Disruption Type Disruption Date Expected Resolve Date Status Remark
1 Aligarh JMC - Kalpataru DHATAULI WSS Dhatauli 20095323/01 Electricity Connection Pending 22-May-2024 - Resolved Payment was done on 22/05/2024, but the electricity connection has not been provided yet.
2 Aligarh JMC - Kalpataru BHARATPUR WSS Bharatpur 20097855/01 Electricity Connection Pending 22-May-2024 - Resolved Payment was done on 22/05/2024, but the electricity connection has not been provided yet.
3 Aligarh PNC-SPML-JV BAINA & RASULPUR WSS Baina 20088512/01 Electricity Connection Pending 04-Aug-2026 08-Oct-2026 Resolved Connection Balance
4 Aligarh PNC-SPML-JV ALAHADADPUR NIVRY WSS Alahadadpur Nivry 20069771/01 Electricity Connection Pending 04-Aug-2026 01-Oct-2026 Resolved Power grid connection balance
5 Baghpat LC INFRA Basi W/S Scheme Basi 20014085/01 Electricity Connection Pending 01-Jul-2024 - Resolved Electrical connection paper pending at Gram Pradhan
6 Barabanki Megha KENHAURA & GULCHAMPKALA Water Supply Scheme Gulchappa Kalan 20094996/01 Electricity Connection Pending 17-Jun-2026 - Pending Electricity Connection Pending
7 Etah ION EXCHANGE Nagla Sukhdev Gram Panchayat Re-Organization W/S Scheme Nagla Sukhdev ZONE01 Electricity Connection Pending 03-Aug-2026 15-Sep-2026 Pending Power connection estimation paid on 18/07/2026, Agreement was done on 30/07/2025, Connection still pending
8 Etah JMC - Kalpataru Bahadurpur kasimpur Water supply scheme Bahadurpur Kasimpur 20098697/01 Electricity Connection Pending 04-Aug-2026 15-Sep-2026 Resolved Public hindrance
9 Etah JMC - Kalpataru Khera Gwarau Water supply scheme Khera Gwarau 20098703/01 Electricity Connection Pending 04-Aug-2026 15-Sep-2026 Resolved Wok not started by UPPCL
10 Etah JMC - Kalpataru Badhavali Gram Panchayat Water Supply Scheme Badhawali 20079513/01 Electricity Connection Pending 04-Aug-2026 15-Sep-2026 Resolved work not started by UPPCL
11 Etah JMC - Kalpataru Loya Badshapur Water supply scheme Loya Badshahpur Peetam Singh 20099319/01 Electricity Connection Pending 04-Aug-2026 15-Sep-2026 Resolved work not started by UPPCL
12 Etah JMC - Kalpataru Kunjalpur water supply scheme Kunjalpur 20100053/01 Electricity Connection Pending 04-Aug-2026 15-Sep-2026 Resolved work not started by UPPCL
13 Etah JMC - Kalpataru Nagaria Urf Sikandarpur Doga water supply scheme Nagaria Urf Sikandarpur Duga 20100049/01 Electricity Connection Pending 04-Aug-2026 15-Sep-2026 Resolved work not started by UPPCL
14 Etah JMC - Kalpataru Saidpur Water supply scheme Saidpur 20098701/01 Electricity Connection Pending 04-Aug-2026 20-Sep-2026 Resolved work not started by UPPCL
15 Etah JMC - Kalpataru MAJHARAU GRAM PANCHAYAT WATER SUPPLY SCHEME Majharau 20079315/01 Electricity Connection Pending 04-Aug-2026 25-Sep-2026 Pending work not started by UPPCL
16 Etah Power Mech Projects Ltd SHITALPUR WATER SUPPLY SCHEME Shitalpur 20086111/01 Electricity Connection Pending 03-Aug-2026 03-Oct-2026 Resolved Payment has to be done.
17 Etawah OMIL-JWIL (JV) KISHONPUR JADONPUR Kishonpur Jadonpur 20099912/01 Electricity Connection Pending 04-Jun-2026 04-Sep-2026 Resolved Electric connection pending.
18 Farrukhabad Vindhya-GAJA (JV) BAGHLAKULA SVS Baglakhula 20097895/01 Electricity Connection Pending 03-Aug-2026 - Pending BAGLAKHULA T/W power connection apply but estimate not received yet from Electrical Department.
19 Fatehpur Power Mech Projects Ltd ADAWAL RO Adawal 20102047/01 Electricity Connection Pending 15-Apr-2026 30-Aug-2026 Resolved Payment Done but Electric Connection Work Not done by Electricity Department.
20 Fatehpur Power Mech Projects Ltd KODAR Kondar 20100809/01 Electricity Connection Pending 15-Apr-2026 30-Aug-2026 Resolved Payment Done but Electric Connection Work Not done by Electricity Department.
21 Hathras BGCCPL-Ramky (JV) DHANDAULI WSS Dhandholi 20071579/01 Electricity Connection Pending 06-Feb-2026 03-Sep-2026 Resolved Dhandauli TW payment done on 06.02.2026. Connection still pending. expected issue resolve Date Given By concern Officer DVVNL in 1 Month
22 Hathras BGCCPL-Ramky (JV) MITANPUR WATER SUPPLY SCHEME Bhogaon Nagla Jayas 20087362/01 Electricity Connection Pending 17-Sep-2024 03-Sep-2026 Resolved Mitanpur TW payment done on 17.09.2024. Connection still pending. expected issue resolve Date Given By concern Officer DVVNL in 1 Month
23 Hathras BGCCPL-Ramky (JV) TIPRAS WSS Tipras 20060549/01 Electricity Connection Pending 16-Sep-2024 03-Sep-2026 Pending Tipras TW payment done on 16.09.2024. Connection still pending. expected issue resolve Date Given By concern Officer DVVNL in 1 Month
24 Hathras BGCCPL-Ramky (JV) KARAIYA WATER SUPPLY SCHEME Karaiya 20061070/01 Electricity Connection Pending 16-Sep-2024 03-Sep-2026 Resolved Karaiya TW payment done on 16.09.2024. Connection still pending. expected issue resolve Date Given By concern Officer DVVNL in 1 Month
25 Hathras BGCCPL-Ramky (JV) DHANOTI WATER SUPPLY SCHEME Dhanothi 20098363/01 Electricity Connection Pending 17-Aug-2024 03-Sep-2026 Resolved Dhanoti TW payment done on 17.08.2024. Connection still pending. expected issue resolve Date Given By concern Officer DVVNL in 1 Month
26 Hathras BGCCPL-Ramky (JV) TONDA WATER SUPPLY SCHEME Tonda 20092744/01 Electricity Connection Pending 14-Mar-2024 - Resolved Tonda TW payment done on 14.03.2024. Connection still pending
27 Hathras ION EXCHANGE RASGAWAN WSS Chamarpur ZONE03 Electricity Connection Pending 04-Aug-2026 15-Sep-2026 Resolved Electric estimation was paid on 6/09/2024. Connection still pending
28 Hathras ION EXCHANGE SHEIKHUPUR AJIT WSS Tataarpur ZONE04 Electricity Connection Pending 04-Aug-2026 15-Sep-2026 Resolved Connection payment was done on 27.06.2023. Connection still pending
29 Hathras ION EXCHANGE RASGAWAN WSS Kheria ZONE04 Electricity Connection Pending 04-Aug-2026 15-Sep-2026 Resolved Connection payment was done on 16.02.2024. Connection still pending
30 Hathras ION EXCHANGE SALEMPUR WSS Madhapithu ZONE02 Electricity Connection Pending 04-Aug-2026 15-Sep-2026 Resolved For Borewell No 1 connection was paid on 19.12.2023. Connection still pending
31 Hathras ION EXCHANGE TASINGA WSS Tasinga ZONE01 Electricity Connection Pending 04-Aug-2026 20-Sep-2026 Resolved Tasinga BW 1 payment done on 21.08.2021. Connection still pending
32 Hathras ION EXCHANGE TASINGA WSS Tasinga ZONE01 Electricity Connection Pending 04-Aug-2026 16-Sep-2026 Resolved Tasinga TW 2 connection payment was done on 21.08.2024. Connection still pending
33 Hathras ION EXCHANGE TASINGA WSS Tasinga ZONE01 Electricity Connection Pending 04-Aug-2026 17-Sep-2026 Resolved Tasinga TW 3 connection payment was done on 06.09.2024. Connection still pending
34 Jaunpur AFCONS AMADAHA GRAM PANCHAYAT WATER SUPPLY SCHEME Amadaha 20095447/01 Electricity Connection Pending 20-Jan-2025 - Pending Payment already done on 20-01-2026 Rs4,69,250
35 Jaunpur AFCONS AHAMADPUR GRAM PANCHAYAT WATER SUPPLY SCHEME Ahamadpur 20086572/01 Electricity Connection Pending 12-Mar-2024 - Pending Payment Done on dated 12.03.2024
36 Jaunpur AFCONS KERAON VILLAGE WATER SUPPLY SCHEME Keraon 20086562/01 Electricity Connection Pending 01-Mar-2024 - Pending Payment Already done on dated 01.03.2024
37 Jaunpur AFCONS UDIASAN URF MUFTU GANJ VILLAGE WATER SUPPLY SCHEME Udiasan Urf Mufti Ganj 20090557/01 Electricity Connection Pending 01-Mar-2024 - Pending UPPCL Estimate 3rd times, we have already paid 1,88,715 & 4,93,295. Again demanded 3,79,390.
38 Jaunpur Welspun Kaveri Infraprojects JV Aunra Aunra 20020925/01 Electricity Connection Pending 25-Aug-2026 - Pending Awarded Land parcel is small, space for Solar installation is not available. Grid connection required for power supply
39 Jaunpur Welspun Kaveri Infraprojects JV Chhunchha Chhunchha 20089683/01 Electricity Connection Pending 25-Aug-2026 - Pending Awarded Land parcel is small, space for Solar installation is not available. Grid connection required for power supply
40 Jaunpur Welspun Kaveri Infraprojects JV Chhunchha Chhunchha 20089683/01 Electricity Connection Pending 15-Mar-2023 - Resolved Awarded Land parcel is small, space for Solar installation is not available. Grid connection required for power supply
41 Jaunpur Welspun Kaveri Infraprojects JV Aunra Aunra 20020925/01 Electricity Connection Pending 23-Nov-2021 - Resolved Awarded Land parcel is small, space for Solar installation is not available. Grid connection required for power supply
42 Kasganj PNC-SPML-JV JAHANGIRPUR Jahangirpur 20101289/01 Electricity Connection Pending 04-Aug-2026 30-Oct-2026 Resolved Approach Road Not Available
43 Kushi Nagar NCC Ltd. GAURI SHRIRAM Gauri Shri Ram 20082320-OHT1 Electricity Connection Pending 30-Jun-2025 20-Oct-2026 Resolved Electricty Connection not done Yet.
44 Kushi Nagar NCC Ltd. GANGAULI GOGP Gangauli 20080227-OHT1 Electricity Connection Pending 30-Jun-2025 10-Nov-2026 Resolved Electricty Connection not done Yet.
45 Kushi Nagar NCC Ltd. AHIROULI RAJA GOGP Ahirauli Raja 20078933-OHT1 Electricity Connection Pending 30-Jun-2025 15-Oct-2026 Resolved Electricty Connection not done Yet.
46 Kushi Nagar NCC Ltd. CHARGAHA Chara Gaha 20078970-OHT1 Electricity Connection Pending 30-Jun-2025 15-Oct-2026 Resolved Electricty Connection not done Yet.
47 Kushi Nagar NCC Ltd. Bharsar Khas Bharsar Khas 20040237-OHT1 Electricity Connection Pending 30-Jun-2025 10-Oct-2026 Resolved Electricity Connection Pending Yet.
48 Kushi Nagar NCC Ltd. BADAHARA BABU-K GOGP Badahara 20078366-OHT1 Electricity Connection Pending 30-Jun-2025 10-Sep-2026 Resolved Electricity Connection Pending yet.
49 Kushi Nagar NCC Ltd. AMDARIA Amadaria 20073033-OHT1 Electricity Connection Pending 30-Jun-2025 15-Sep-2026 Resolved Electricity conection Pending Yet
50 Kushi Nagar NCC Ltd. CHANDARPUR Chandarpur 20082193-OHT1 Electricity Connection Pending 30-Jun-2025 10-Sep-2026 Resolved Electricity Connection Pending.
51 Kushi Nagar NCC Ltd. INDERSENWA Ramkola 20097181-OHT1 Electricity Connection Pending 30-Jun-2025 11-Nov-2026 Resolved Electricity Connection Pending yet.
52 Kushi Nagar NCC Ltd. SIDHAWE Sidhawe 20082263-OHT1 Electricity Connection Pending 30-Jun-2025 10-Sep-2026 Resolved Electricity Connection Pending Yet.
53 Kushi Nagar NCC Ltd. RAMPUR BAGAHA Rampur Bagaha 20082305-OHT1 Electricity Connection Pending 03-Jun-2025 15-Sep-2026 Resolved Electricty Connection not done Yet.
54 Kushi Nagar NCC Ltd. AWARAHI KRITPURA Awarahi Kritpura 20082087-OHT1 Electricity Connection Pending 03-Jun-2025 10-Oct-2026 Resolved Electricty Connection not done Yet.
55 Kushi Nagar NCC Ltd. MORWAN Morwan 20073407-OHT1 Electricity Connection Pending 03-Jun-2025 15-Oct-2026 Resolved Electricaity Connection Pending yet.
56 Kushi Nagar NCC Ltd. BINDUAR Binduar 20081809-OHT1 Electricity Connection Pending 03-Jun-2025 15-Sep-2026 Resolved Electricity connection Pending yet.
57 Kushi Nagar NCC Ltd. SAURAHA BUZURG Saurha Buzurg 20073432-OHT1 Electricity Connection Pending 03-Jun-2025 15-Oct-2026 Resolved Electricty Connection not done Yet.
58 Kushi Nagar NCC Ltd. POKHAR BHINDA Pokhar Bhinda 20101611-OHT1 Electricity Connection Pending 16-Dec-2024 10-Oct-2026 Resolved Electricty Connection not done Yet.
59 Kushi Nagar NCC Ltd. NAKATAHA BASDILA Nakataha Basdila 20097035-OHT1 Electricity Connection Pending 04-Oct-2024 15-Oct-2026 Resolved Electricty Connection not done Yet.
60 Kushi Nagar NCC Ltd. AHIRAULI Ahiraule 20106859-OHT1 Electricity Connection Pending 04-Jun-2024 15-Oct-2026 Resolved Electricty Connection not done Yet.
61 Kushi Nagar NCC Ltd. GAURI SHUKUL Gauri Sukul 20102417-OHT1 Electricity Connection Pending 04-Jun-2024 20-Oct-2026 Resolved Electricty Connection not done Yet.
62 Kushi Nagar NCC Ltd. KHAIRATIYA Jalal Chhapra 20106713-OHT1 Electricity Connection Pending 04-Jun-2024 30-Oct-2026 Resolved Electricty Connection not done Yet.
63 Kushi Nagar NCC Ltd. MALHO Tulsi Patti 8388204-OHT1 Electricity Connection Pending 04-Jun-2024 20-Nov-2026 Resolved Electricty Connection not done Yet.
64 Kushi Nagar NCC Ltd. PATHARWA Patharwa 20042728-OHT1 Electricity Connection Pending 04-Jun-2024 20-Oct-2026 Resolved Electricty Connection not done Yet.
65 Kushi Nagar NCC Ltd. RAKBAJUNGLI PATTI R Rakbajunglli Patti 20098913-OHT1 Electricity Connection Pending 04-Jun-2024 15-Oct-2026 Resolved Electricty Connection not done Yet.
66 Kushi Nagar NCC Ltd. PARASAUNI BUZURG RO Parasauni Buzurg 20098932-OHT1 Electricity Connection Pending 04-Jun-2024 15-Oct-2026 Resolved Electricty Connection not done Yet.
67 Kushi Nagar NCC Ltd. GANESH PATTI Ganesh Patti 20102413-OHT1 Electricity Connection Pending 04-Jun-2024 20-Oct-2026 Resolved Electricty Connection not done Yet.
68 Kushi Nagar NCC Ltd. BHIURA BHIURA 20106858-OHT1 Electricity Connection Pending 04-Jun-2024 16-Oct-2026 Resolved Electricty Connection not done Yet.
69 Kushi Nagar NCC Ltd. KATAURA Kataura 20101609-OHT1 Electricity Connection Pending 04-Jun-2024 10-Nov-2026 Resolved Electricity connection not done yet.
70 Kushi Nagar NCC Ltd. MATHIA MAFI RO Mathiamafi Urf Dukhi Ganeshpur 20102430-OHT1 Electricity Connection Pending 04-Jun-2024 20-Oct-2026 Resolved Electricty Connection not done Yet.
71 Kushi Nagar NCC Ltd. MALHO Tulsi Patti 8388204-OHT1 Electricity Connection Pending 04-Jun-2024 25-Dec-2026 Resolved Electricty Connection not done Yet.
72 Kushi Nagar NCC Ltd. GANESH PATTI Ganesh Patti 20102413-OHT1 Electricity Connection Pending 04-Jun-2024 15-Dec-2026 Resolved Electricty Connection not done Yet.
73 Kushi Nagar NCC Ltd. PARASAUNI BUZURG RO Parasauni Buzurg 20098932-OHT1 Electricity Connection Pending 04-Jun-2024 25-Dec-2026 Resolved Electricty Connection not done Yet.
74 Kushi Nagar NCC Ltd. PATHARWA Patharwa 20042728-OHT1 Electricity Connection Pending 04-Jun-2024 25-Dec-2026 Resolved Electricty Connection not done Yet.
75 Kushi Nagar NCC Ltd. PATERHA Paterha 20102431-OHT1 Electricity Connection Pending 06-Apr-2024 10-Sep-2026 Resolved Electricity connection pending yet
76 Kushi Nagar NCC Ltd. PIPRAGHAT Pipraghat Ahatmali 20097042-OHT1 Electricity Connection Pending 02-Mar-2024 15-Oct-2026 Resolved Electricty Connection not done Yet.
77 Kushi Nagar NCC Ltd. PIPRAGHAT Pipraghat Ahatmali 20097042-OHT1 Electricity Connection Pending 02-Mar-2024 25-Dec-2026 Resolved Electricty Connection not done Yet.
78 Kushi Nagar NCC Ltd. PAKRI BRIJLAL Pakari Brijlal No.2 8386824-OHT1 Electricity Connection Pending 20-Feb-2024 15-Oct-2026 Resolved Electricty Connection not done Yet.
79 Kushi Nagar NCC Ltd. SISWA GOPAL Siswa Gopal 20050914-OHT1 Electricity Connection Pending 20-Feb-2024 15-Oct-2026 Resolved Electricty Connection not done Yet.
80 Kushi Nagar NCC Ltd. BRINDABAN Brindaban 20040280-OHT1 Electricity Connection Pending 20-Feb-2024 15-Sep-2026 Resolved Electrical Connection Pending
81 Kushi Nagar NCC Ltd. GANGRAI Gangrai 20102428-OHT1 Electricity Connection Pending 20-Feb-2024 15-Sep-2026 Resolved Electricty Connection not done Yet.
82 Kushi Nagar NCC Ltd. VIJAIPUR Vijaipur 20051261-OHT1 Electricity Connection Pending 20-Feb-2024 10-Oct-2026 Resolved electricity connection pending yet.
83 Kushi Nagar NCC Ltd. KUCHAYA RO KUCHAYA 20098937-OHT1 Electricity Connection Pending 16-Feb-2024 10-Sep-2026 Resolved Electricty Connection not done Yet.
84 Kushi Nagar NCC Ltd. RAHASUJANUBI PATTI R Rahasujanubi Patti 20098931-OHT1 Electricity Connection Pending 16-Feb-2024 15-Sep-2026 Resolved Electricty Connection not done Yet.
85 Kushi Nagar NCC Ltd. PADRI MEHDIA Padri Mehdia 20101619-OHT1 Electricity Connection Pending 16-Feb-2024 25-Sep-2026 Resolved Electricty Connection not done Yet.
86 Kushi Nagar NCC Ltd. KURMAUL Urf SOHANPUR Kurmaul Urf Sohanpur 20098904-OHT1 Electricity Connection Pending 16-Feb-2024 15-Oct-2026 Resolved Electricty Connection not done Yet.
87 Kushi Nagar NCC Ltd. KURMAUL Urf SOHANPUR Kurmaul Urf Sohanpur 20098904-OHT1 Electricity Connection Pending 16-Feb-2024 30-Dec-2026 Resolved Electricty Connection not done Yet.
88 Kushi Nagar NCC Ltd. PARSA URF SIRSIA Parsa Ahatmali 20042706-OHT1 Electricity Connection Pending 03-Feb-2024 25-Dec-2026 Resolved Electricty Connection not done Yet.
89 Kushi Nagar NCC Ltd. CHAKIA SOBHMAL Chakia 8388387-OHT1 Electricity Connection Pending 03-Feb-2024 15-Oct-2026 Resolved Electricty Connection not done Yet.
90 Kushi Nagar NCC Ltd. PARSADPUR Parsadpur 20101605-OHT1 Electricity Connection Pending 03-Feb-2024 10-Nov-2026 Resolved Electricty Connection not done Yet.
91 Kushi Nagar NCC Ltd. PARSA URF SIRSIA Parsa Ahatmali 20042706-OHT1 Electricity Connection Pending 03-Feb-2024 15-Oct-2026 Resolved Electricty Connection not done Yet.
92 Kushi Nagar NCC Ltd. BIRWAT KOMWALIA R Birwat Komwalia 20098928-OHT1 Electricity Connection Pending 03-Feb-2024 15-Oct-2026 Resolved Electricty Connection not done Yet.
93 Lucknow NCC Ltd. Narendi Water Supply Scheme Narendi 20070143/01 Electricity Connection Pending 25-Mar-2026 - Resolved Due to Non Providing of Estimate, we are unable to supply the water to villages
94 Lucknow NCC Ltd. Dedhari, Rampur Garhi Jamuni & Bramhdas Pur Bramhedas Pur 20070391/01 Electricity Connection Pending 20-Mar-2026 - Resolved Due to Non Providing of Electricity power, we are unable to supply the water to villages
95 Lucknow NCC Ltd. Lonha Lonha 8360588/01 Electricity Connection Pending 06-Mar-2026 - Resolved Due to Non Providing of Estimate, we are unable to supply the water to villages
96 Lucknow NCC Ltd. Papnamau Papnamau 20015648/01 Electricity Connection Pending 03-Mar-2026 - Resolved Due to Non Providing of Estimate, we are unable to supply the water to villages
97 Lucknow NCC Ltd. Bhadeshwa & Dhanuwa Sand Bhadeshwa 20070387/01 Electricity Connection Pending 13-Feb-2026 - Resolved Due to Non Providing of Electricity power, we are unable to supply the water to villages.
98 Lucknow NCC Ltd. Pahiaajampur Pahiaajampur 20070064/01 Electricity Connection Pending 07-Feb-2026 - Resolved Due to Non Providing of Estimate, we are unable to supply the water to villages
99 Muzaffarnagar JMC - Lakshmi (JV) HARENTI SALEMPUR Harenti 20062927/01 Electricity Connection Pending 04-Aug-2026 - Pending The villagers are opposing of the electric line
100 Muzaffarnagar JMC - Lakshmi (JV) GHISUKHERA Ghisukhera 20039787/01 Electricity Connection Pending 04-Aug-2026 - Pending The villagers are opposing of the electric line
101 Pilibhit VISHVARAJ Parsadpur+1 Multi GP water supply scheme Parsadpur 20096350/01 Electricity Connection Pending 13-Mar-2026 - Pending Estimate amount paid to UPPCL, but electrical connection is still pending.
102 Pilibhit VISHVARAJ SIRSA GP WATER SUPPLY SCHEME Sirsa 20051046/01 Electricity Connection Pending 14-Jan-2026 - Pending Estimate amount paid to UPPCL, but electrical connection is still pending.
103 Pilibhit VISHVARAJ PIPARI AGROO GP WATER SUPPLY SCHEME Pipria Agru 20096590/01 Electricity Connection Pending 14-Jan-2026 - Pending Estimate amount paid to the UPPCL but, electrical connection is still pending, which is hampering the regular water supply.
104 Pilibhit VISHVARAJ khamaria pandari water supply scheme Khamaria Pandri 20096325/01 Electricity Connection Pending 20-Oct-2025 - Pending Estimate amount paid to UPPCL, but electrical connection is still pending.
105 Pilibhit VISHVARAJ Parsadpur+1 Multi GP water supply scheme Parsadpur 20096350/01 Electricity Connection Pending 05-Oct-2024 - Resolved Estimate amount paid to UPPCL, but electrical connection is still pending.
106 Pilibhit VISHVARAJ khamaria pandari water supply scheme Khamaria Pandri 20096325/01 Electricity Connection Pending 05-Oct-2024 - Resolved Estimate amount paid to UPPCL, but electrical connection is still pending.
107 Rampur PNC SPML- JV Moradabad BALPURA VILL W/S SCHEME Balpura 20096263 Electricity Connection Pending 04-Aug-2026 - Resolved Pending after TC amount deposited to UPPCL
108 Sant Ravidas Nagar Welspun Kaveri Infraprojects JV Poore Vishvanath Multi GP Water Supply Scheme Harihar Pursoni 20024596/01 Electricity Connection Pending 25-Nov-2021 30-Aug-2026 Resolved HT Line shifting pending for commencement of construction activities