| S.No. | District | Agency | Scheme | Village | OHT Code | Disruption Type | Disruption Date | Expected Resolve Date | Status | Remark |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Shahjahanpur | NCC Ltd. | KHIRIA RATAN | Khiria Ratan | 20016531/01 | NOC Pending (NHAI/Railway/Forest/Irrigation/State Highway/IOCL/IGL/HPCL/UPEIDA/UPPCL/GAIL) | 14-Aug-2026 | 30-Jun-2028 | Pending | The current physical progress of the scheme in Gram Panchayat Khiriya Ratan is 65%. As per CIRP, the scheduled date for completion of all scheme works is March 2028. Regarding obtaining the NOC, the requisite documents have again been forwarded to the Project Director, NHAI, PIU Green Park (Bareilly), through Block Office Letter No. 1383/W.S.-10/71 dated 21.04.2026 and Letter No. 6879/W.S.-1/02 dated 12.10.2026. The matter has also been brought to their notice through personal discussions. However, no positive response has been received so far. |
| 2 | Shahjahanpur | NCC Ltd. | AMANPUR WSS | Amanpur | 20071368/01 | NOC Pending (NHAI/Railway/Forest/Irrigation/State Highway/IOCL/IGL/HPCL/UPEIDA/UPPCL/GAIL) | 14-Aug-2026 | 30-Jun-2028 | Pending | The current physical progress of the scheme in Gram Panchayat Amanpur is 65%. As per CIRP, the scheduled date for completion of all scheme works is March 2028. Regarding obtaining the NOC, the requisite documents have again been forwarded to the Project Director, NHAI, PIU Green Park (Bareilly), through Block Office Letter No. 1383/W.S.-10/71 dated 21.04.2026 and Letter No. 6879/W.S.-1/02 dated 12.10.2026. The matter has also been brought to their notice through personal discussions. However, no positive response has been received so far. |
| 3 | Shahjahanpur | NCC Ltd. | CHAUKHUTIA & KAKRALA & ATIWARA WSS | Kakrala | 20073329/01 | NOC Pending (NHAI/Railway/Forest/Irrigation/State Highway/IOCL/IGL/HPCL/UPEIDA/UPPCL/GAIL) | 14-Aug-2026 | 30-Jun-2028 | Pending | The current physical progress of the scheme in Gram Panchayat Kakrala is 50%. As per CIRP, the scheduled date for completion of all scheme works is March 2028. Regarding obtaining the NOC, the requisite documents have again been forwarded to the Project Director, NHAI, PIU Green Park (Bareilly), through Block Office Letter No. 1383/W.S.-10/71 dated 21.04.2026 and Letter No. 6879/W.S.-1/02 dated 12.10.2026. The matter has also been brought to their notice through personal discussions. However, no positive response has been received so far. |
| 4 | Shahjahanpur | NCC Ltd. | ABHAIN & BARUA BUZURG MULTI GRAM PANCHAYAT MULTI VILLAGE WATER SUPPLY SCHEME | Abhain | 20084188/01 | NOC Pending (NHAI/Railway/Forest/Irrigation/State Highway/IOCL/IGL/HPCL/UPEIDA/UPPCL/GAIL) | 14-Aug-2026 | 30-Jun-2028 | Pending | The current physical progress of the scheme in Gram Panchayat Abhain is 55%. As per CIRP, the scheduled date for completion of all scheme works is March 2028. Regarding obtaining the NOC, the requisite documents have again been forwarded to the Project Director, NHAI, PIU Green Park (Bareilly), through Block Office Letter No. 1383/W.S.-10/71 dated 21.04.2026 and Letter No. 6879/W.S.-1/02 dated 12.10.2026. The matter has also been brought to their notice through personal discussions. However, no positive response has been received so far. |
| 5 | Shahjahanpur | NCC Ltd. | KUTUAPUR ELAQUA SAHERAMAU GRAM PANCHAYAT MULTI VILLAGE WATER SUPPLY SCHEME | Kutuapur Elaqua Saheramau | 20096533/01 | NOC Pending (NHAI/Railway/Forest/Irrigation/State Highway/IOCL/IGL/HPCL/UPEIDA/UPPCL/GAIL) | 14-Aug-2026 | 30-Jun-2028 | Pending | The current physical progress of the scheme in Gram Panchayat Kutwapur Elaqua Sheramau is 55%. As per CIRP, the scheduled date for completion of all scheme works is March 2028. Regarding obtaining the NOC, the requisite documents have again been forwarded to the Project Director, NHAI, PIU Green Park (Bareilly), through Block Office Letter No. 1383/W.S.-10/71 dated 21.04.2026 and Letter No. 6879/W.S.-1/02 dated 12.10.2026. The matter has also been brought to their notice through personal discussions. However, no positive response has been received so far. |
| 6 | Shahjahanpur | NCC Ltd. | PATNA WSS | Patna | 20078973/01 | NOC Pending (NHAI/Railway/Forest/Irrigation/State Highway/IOCL/IGL/HPCL/UPEIDA/UPPCL/GAIL) | 14-Aug-2026 | 30-Jun-2028 | Pending | The current physical progress of the scheme in Gram Panchayat Patna is 30%. As per CIRP, the scheduled date for completion of all scheme works is March 2028. It is also submitted that since the beginning, local villagers have been continuously creating obstructions due to a land-related dispute in the said Gram Panchayat, which has adversely affected the progress of the scheme works. Regarding obtaining the NOC, the requisite documents have again been forwarded to the Project Director, NHAI, PIU Green Park (Bareilly), through Block Office Letter No. 1383/W.S.-10/71 dated 21.04.2026 and Letter No. 6879/W.S.-1/02 dated 12.10.2026. The matter has also been brought to their notice through personal discussions. However, no positive response has been received so far. |
| 7 | Shahjahanpur | NCC Ltd. | FIROZPUR GRAM PANCHAYAT MULTI VILLAGE WATER SUPPLY SCHEME | Vilhara | 20084338/01 | NOC Pending (NHAI/Railway/Forest/Irrigation/State Highway/IOCL/IGL/HPCL/UPEIDA/UPPCL/GAIL) | 14-Aug-2026 | 30-Jun-2028 | Pending | The current physical progress of the scheme in Gram Panchayat Firozpur is 65%. As per CIRP, the scheduled date for completion of all scheme works is March 2028. Regarding obtaining the NOC, the requisite documents have again been forwarded to the Project Director, NHAI, PIU Green Park (Bareilly), through Block Office Letter No. 1383/W.S.-10/71 dated 21.04.2026 and Letter No. 6879/W.S.-1/02 dated 12.10.2026. The matter has also been brought to their notice through personal discussions. However, no positive response has been received so far. |
| 8 | Shahjahanpur | NCC Ltd. | DADIURA & NIYAMATPUR MULTI GRAM PANCHAYAT MULTI VILLAGE WATER SUPPLY SCHEME | Dadiura | 20084170/01 | Water Logged / Flood-Prone Area / Natural Calamity | 05-Aug-2026 | 30-Oct-2028 | Pending | In view of the natural changes in the river course and the possibility of erosion, the site was considered vulnerable from a safety perspective. Accordingly, the OHT was dismantled, making relocation of the OHT necessary. The firm has requested the allotment of alternative government land, and necessary action is being taken in coordination with the Tehsil authorities. |
| 9 | Shahjahanpur | NCC Ltd. | VIKRAMPUR CHAKAURA Nigohi W/s | Vikrampur Chakaura | 20015058/01 | Water Logged / Flood-Prone Area / Natural Calamity | 05-Aug-2026 | 31-Oct-2028 | Pending | In view of the natural changes in the river course and the possibility of erosion, the site was considered vulnerable from a safety perspective. Accordingly, the OHT was dismantled, making relocation of the OHT necessary. The firm has requested the allotment of alternative government land, and necessary action is being taken in coordination with the Tehsil authorities. |
| 10 | Shahjahanpur | NCC Ltd. | Dhubla Karimnagar | Dhuvla Karimnagar | 20019783/01 | Water Logged / Flood-Prone Area / Natural Calamity | 05-Aug-2026 | 30-Jun-2028 | Pending | The scheme area is located in a waterlogged/flood-prone area, where the pump house and solar-related works have already been completed. Consequently, the progress of the remaining construction activities is likely to be affected during the rainy season/floods. The firm has requested the allotment of alternative government land, and necessary action is being taken in coordination with the Tehsil authorities. |
| 11 | Shahjahanpur | NCC Ltd. | BENIPUR WSS | Benipur | 20058760/01 | Land Dispute / Litigation | 05-Aug-2026 | 30-Jun-2028 | Pending | There is no road access to the scheme site. At present, the tubewell boring work has been completed; however, the remaining construction activities are obstructed. The firm has requested the allotment of alternative government land, and necessary action is being taken in coordination with the Tehsil authorities. |
| 12 | Shahjahanpur | NCC Ltd. | DOSHPUR THOK GRAM PANCHAYAT WATER SUPPLY SCHEME | Doshpur Thok | 20101596/01 | Saline Water / Poor Water Source(Salinity/Fluoride/Iron) | 05-Aug-2026 | 30-Jun-2028 | Pending | Tubewell boring has been carried out once/twice/thrice; however, saline water was encountered on each occasion. Additional land is required for another bore. The firm has requested the allotment of alternative government land, and necessary action is being taken in coordination with the Tehsil authorities. |
| 13 | Shahjahanpur | NCC Ltd. | JAITIPUR GRAM PANCHAYAT MULTI VILLAGE WATER SUPPLY SCHEME | Jaitipur | 8361729/01 | Water Logged / Flood-Prone Area / Natural Calamity | 05-Aug-2026 | 31-Oct-2028 | Pending | In view of the natural changes in the river course and the possibility of erosion, the site was considered vulnerable from a safety perspective. Accordingly, the OHT was dismantled, making relocation of the OHT necessary. The firm has requested the allotment of alternative government land, and necessary action is being taken in coordination with the Tehsil authorities. |
| 14 | Shahjahanpur | NCC Ltd. | VAIDAPUR MULTI GRAM PANCHAYAT MULTI VILLAGE WATER SUPPLY SCHEME | Paidapur | 20084382/01 | Water Logged / Flood-Prone Area / Natural Calamity | 05-Aug-2026 | 30-Jun-2028 | Pending | The scheme area is located in a waterlogged/flood-prone area, where the pump house/OHT works have been completed up to the plinth level. Consequently, the progress of the remaining construction activities is likely to be affected during the rainy season/floods. The firm has requested the allotment of alternative government land, and necessary action is being taken in coordination with the Tehsil authorities. |
| 15 | Shahjahanpur | NCC Ltd. | BEHTI GP MULTI VILLAGE WSS | Behti | 20093768/01 | Land Dispute / Litigation | 05-Aug-2026 | 31-Oct-2028 | Pending | Due to a local dispute over the land allotted in Village Behti, the matter was taken to the Hon’ble High Court, which subsequently passed a stay order. At present, the tubewell boring work has been completed; however, the remaining construction activities are held up. The firm has requested the allotment of alternative government land, and necessary action is being taken in coordination with the Tehsil authorities. |
| 16 | Shahjahanpur | NCC Ltd. | SITHARA GP MULTI VILLAGE WSS | Sithara | 20093790/01 | Public Hindrance / Local Hindrance | 05-Aug-2026 | 30-Jun-2028 | Pending | It is submitted that, due to a land-related dispute in the said Gram Panchayat, local villagers are raising objections to the commencement of the work. The tubewell boring work within the premises has been completed; however, the progress of subsequent construction activities is being affected. In view of these circumstances, the firm has requested the allotment of alternative government land, and necessary action is being taken in coordination with the Tehsil authorities. |
| 17 | Shahjahanpur | NCC Ltd. | RAMPUR GP WSS | Rampur | 20099668/01 | Water Logged / Flood-Prone Area / Natural Calamity | 05-Aug-2026 | 31-Oct-2028 | Pending | The scheme area is located in a waterlogged/flood-prone area, where the pump house and solar-related works have already been carried out. Consequently, the progress of the remaining construction activities is likely to be affected during the rainy season/floods. The firm has requested the allotment of alternative government land, and necessary action is being taken in coordination with the Tehsil authorities. |
| 18 | Shahjahanpur | NCC Ltd. | MAU VASAK GRAM PANCHAYAT VILLAGE WATER SUPPLY SCHEME | Mau Vasak | 20096496/01 | Land Dispute / Litigation | 05-Aug-2026 | 30-Jun-2028 | Pending | The land was allotted in close proximity to the Army Cantonment premises, where the pump house construction had already been completed. However, in view of security concerns, the Army administration has imposed restrictions on further construction activities. The firm has requested the allotment of alternative government land, and necessary action is being taken in coordination with the Tehsil authorities. |
| 19 | Shahjahanpur | NCC Ltd. | SHAHVEGNAGAR GRAM PANCHAYAT VILLAGE WATER SUPPLY SCHEME | Shahvegpur | 20097898/01 | Public Hindrance / Local Hindrance | 05-Aug-2026 | 31-Oct-2027 | Pending | It is submitted that, due to a land-related dispute in the said Gram Panchayat, objections have been raised by local residents against the commencement of the work. The tubewell boring work within the premises has been completed; however, the progress of subsequent construction activities is being affected. In view of these circumstances, the firm has requested the allotment of alternative government land, and necessary action is being taken in coordination with the Tehsil authorities. |