8010056 |
Saidpur Kumheri GOV |
OHT0007 |
Lalitpur |
Mahroni |
Kumehri |
Kumehri |
Road Widening |
01-May-2025 |
07-Sep-2025 |
the ESR 250mm CWRM pipe was damaged by the PWD, due to which the supply to the entire zone is suspended. The pipe will be re-laid in till first week of September , and the supply from the ESR will be resumed.
The 300mm distribution pipe, which supplies Kumehri, Boosra, and Baron villages, has also been damaged by the PWD department. |
| 2 |
8010056 |
Saidpur Kumheri GOV |
OHT0007 |
Lalitpur |
Mahroni |
Baron |
Baron |
Road Widening |
01-May-2025 |
07-Sep-2025 |
the ESR pipe was damaged by the PWD, due to which the supply to the entire zone is suspended. The pipe will be relaid in till fisrt week of September , and the supply from the ESR will be resumed. |
| 3 |
8010056 |
Saidpur Kumheri GOV |
OHT0007 |
Lalitpur |
Mahroni |
Baron |
Bhoosra |
Road Widening |
01-May-2025 |
07-Sep-2025 |
the ESR 250mm CWRM pipe was damaged by the PWD, due to which the supply to the entire zone is suspended. The pipe will be re-laid in till first week of September , and the supply from the ESR will be resumed.
The 300mm distribution pipe, which supplies Kumehri, Boosra, and Baron villages, has also been damaged by the PWD department. |