| 1 |
8153338 |
Dhauha GOV |
ESR 12 |
Mirzapur |
Rajgarh |
Ban Imiliya |
Ban Imiliya |
Road Widening[PWD] |
08-Jan-2026 |
31-Aug-2026 |
Pipeline laying work is already in progress, due to which water supply to 7 habitations has been affected and is currently interrupted |
| 2 |
8153338 |
Dhauha GOV |
ESR 14 |
Mirzapur |
Rajgarh |
Rampur Sakteshgarh |
Rampur Sakteshgarh |
Road Widening[PWD] |
08-Jan-2026 |
31-Aug-2026 |
Pipeline laying work is already in progress, due to which water supply to 3 habitations has been affected and is currently interrupted |
| 3 |
8153338 |
Dhauha GOV |
ESR 14 |
Mirzapur |
Rajgarh |
Kothilawa |
Kothilawa |
Road Widening[PWD] |
14-Jul-2026 |
|
The pipeline was damaged by the PWD during the road widening work. |