| Sr No. | Scheme Code | Scheme Name | OHT Code | District | Block | Panchayat | Village | Issue Type | Issue Date | Expected Issue Resolve Date | Remark |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 8153338 | Dhauha GOV | ESR 12 | Mirzapur | Rajgarh | Ban Imiliya | Ban Imiliya | Road Widening[PWD] | 08-Jan-2026 | 31-Aug-2026 | Pipeline laying work is already in progress, due to which water supply to 7 habitations has been affected and is currently interrupted |
| 2 | 8153338 | Dhauha GOV | ESR 14 | Mirzapur | Rajgarh | Rampur Sakteshgarh | Rampur Sakteshgarh | Road Widening[PWD] | 08-Jan-2026 | 31-Aug-2026 | Pipeline laying work is already in progress, due to which water supply to 3 habitations has been affected and is currently interrupted |
| 3 | 8153338 | Dhauha GOV | ESR 21 | Mirzapur | Narainpur | Rupaudha | Rupaudha | Road Widening[PWD] | 04-Mar-2026 | 30-Jul-2026 | The pipeline was damaged by the PWD during the road widening work. |