| 1 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Bijaigarh |
424200 |
Bagroni Jagir |
Theft |
01-Aug-2025 |
|
Scada Instrument Panel Inverter & Battery Theft on 31-07-2025 |
| 2 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Imilia |
424211 |
Imilia |
Theft |
01-Aug-2025 |
|
Scada Instrument Panel Inverter & Battery Theft on 31-07-2025 |
| 3 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Charhrau Dhawari |
424212 |
Satpura |
Theft |
01-Aug-2025 |
|
Scada Instrument Panel Inverter & Battery Theft on 31-07-2025 |
| 4 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Sanaura |
424242 |
Amanpura |
Theft |
01-Aug-2025 |
|
Scada Instrument Panel Inverter & Battery Theft on 31-07-2025 |
| 5 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Sanaura |
424243 |
Bar Urf Rampur |
Theft |
01-Aug-2025 |
|
Scada Instrument Panel Inverter & Battery Theft on 31-07-2025 |
| 6 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Ninaura |
424230 |
Ninaura |
Road Widening[PWD] |
01-Jul-2026 |
|
PWD has damaged the pipeline from last 2.5 years. Work started on 01-05-2026 due to the intervention of ACS sir and DM Jhansi. However the same has been stopped due to rainy season. |
| 7 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Arjar |
424226 |
Arjar |
Road Widening[PWD] |
01-Jul-2026 |
|
PWD has damaged the pipeline from last 2.5 years. Work started on 01-05-2026 due to the intervention of ACS sir and DM Jhansi. However the same has been stopped due to rainy season. |
| 8 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Arjar |
424226 |
Arjar |
Road Widening[PWD] |
01-Jul-2026 |
|
PWD Repairing work stopped due to rainy season |
| 9 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Arjar |
424227 |
Rampura |
Road Widening[PWD] |
01-Jul-2026 |
|
PWD Repairing work stopped due to rainy season. |
| 10 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Arjar |
424227 |
Rampura |
Road Widening[PWD] |
01-Jul-2026 |
|
PWD has damaged the pipeline from last 2.5 years. Work started on 01-05-2026 due to the intervention of ACS sir and DM Jhansi. However the same has been stopped due to rainy season. |
| 11 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Arjar |
424227 |
Rampura |
Road Widening[PWD] |
01-May-2026 |
|
PWD has damaged the pipeline from last 2.5 years. As per the instruction of ACS sir, joint meeting was conducted by DM Jhansi. There after joint site inspection was conducted by CE- UPJN and CE- PWD and there after work has been started by PWD. |
| 12 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Arjar |
424226 |
Arjar |
Road Widening[PWD] |
01-May-2026 |
|
PWD has damaged the pipeline from last 2.5 years. As per the instruction of ACS sir, joint meeting was conducted by DM Jhansi. There after joint site inspection was conducted by CE- UPJN and CE- PWD and there after work has been started by PWD. |
| 13 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Arjar |
424226 |
Arjar |
Road Widening[PWD] |
01-May-2026 |
|
PWD has started attending repairs after intervention of DM Jhansi |
| 14 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Arjar |
424227 |
Rampura |
Road Widening[PWD] |
01-May-2026 |
|
PWD has started attending repairs after intervention of DM Jhansi |
| 15 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Ninaura |
424230 |
Ninaura |
Road Widening[PWD] |
01-May-2026 |
|
PWD has damaged the pipeline from last 2.5 years. As per the instruction of ACS sir, joint meeting was conducted by DM Jhansi. There after joint site inspection was conducted by CE- UPJN and CE- PWD and there after work has been started by PWD at Arjar and Rampura. Work at Ninaura will be started after completion of above two villages. |
| 16 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Arjar |
424227 |
Rampura |
Road Widening[PWD] |
05-Oct-2026 |
|
The damaged pipeline in Village Rampura has been repaired by the PWD, and water supply has been restored to 36 FHTCs. After completing the interconnection work of the village branch pipeline, 100% water supply can be ensured in the village.
However, the PWD has stopped the work since 20 September, due to which the interconnection work of the branch pipeline remains pending and 100% water supply in the village could not be started. |
| 17 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Ninaura |
424230 |
Ninaura |
Road Widening[PWD] |
10-Jan-2024 |
|
Pwd has damaged the pipeline from last 1.5 years and still not repaired it till now. |
| 18 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Ninaura |
424230 |
Ninaura |
Road Widening[PWD] |
10-Jan-2024 |
|
PWD has damaged the pipeline from last 2.5 years. As per the instruction of ACS sir, joint meeting was conducted by DM Jhansi. There after joint site inspection was conducted by CE- UPJN and CE- PWD and there after work has been started by PWD on 01-05-2026. However the work has been stopped due to rainy season for two months. Due to the intervention of MD-UPJN and DM Jhansi on 01-09-2026. Work at Ninaura will be started after completion of water supply to Arjar & Rampura. The completion date will be finalised during the meeting called by DM Jhansi on 23-09-2026. |
| 19 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Ninaura |
424230 |
Ninaura |
Road Widening[PWD] |
10-Jan-2024 |
|
PWD has damaged the pipeline from last 2.5 years. As per the instruction of ACS sir, joint meeting was conducted by DM Jhansi. There after joint site inspection was conducted by CE- UPJN and CE- PWD and there after work has been started by PWD on 01-05-2026. However the work has been stopped due to rainy season for two months. Due to the intervention of MD-UPJN and DM Jhansi on 01-09-2026 work at Arjar & Rampura started. Work at Ninaura will be started after completion of water supply to above two villages. The completion date will be finalised during the meeting called by DM Jhansi on 23-09-2026. |
| 20 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Ninaura |
424230 |
Ninaura |
Road Widening[PWD] |
10-Jan-2024 |
|
PWD has damaged the pipeline, and the issue has remained unresolved for the last 2.5 years. After the intervention of the ACS Sir, a joint meeting of both departments was conducted by the DM, Jhansi.
Thereafter, a joint site inspection was carried out by the Chief Engineer (CE), UPJN, and CE, PWD. It was mutually agreed that the pipeline-laying work would be carried out by PWD under the supervision of UPJN and the firm.
Accordingly, PWD started the work on 01.05.2026. However, the work was stopped due to the rainy season and was not resumed thereafter.
Following the intervention of the MD sir - UPJN (R), the DM - Jhansi, convened a meeting with both departments, and the work was resumed on 01.09.2026. Repair woks will be started in this village after completion of works at Arjar & Rampura Villages
The completion date will be finalized during the meeting convened by the DM, Jhansi, on 23.09.2026. |
| 21 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Ninaura |
424230 |
Ninaura |
Road Widening[PWD] |
10-Jan-2024 |
31-Oct-2026 |
PWD has damaged the pipeline, and the issue has remained unresolved for the last 2.5 years. After the intervention of the ACS Sir, a joint meeting of both departments was conducted by the DM, Jhansi. Thereafter, a joint site inspection was carried out by the Chief Engineer (CE), UPJN, and CE, PWD. It was mutually agreed that the pipeline-laying work would be carried out by PWD under the supervision of UPJN and the firm. Accordingly, PWD started the work on 01.05.2026. However, the work was stopped due to the rainy season and was not resumed thereafter. Following the intervention of the MD sir - UPJN (R), the DM - Jhansi, convened a meeting with both departments, and the work was resumed on 01.09.2026. The work is currently in progress. The completion date will be finalized during the meeting convened by the DM, Jhansi, on 23.09.2026.In this meeting DM has directed to PWD remaining works would be completed as soon as possible.In complaince PWD stated that the remaining works will take 1 month for complaince . |
| 22 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Ninaura |
424230 |
Ninaura |
Road Widening[PWD] |
10-Jan-2024 |
|
1. PWD has damaged the pipe line during road widening in 2024. and the issue has remained unresolved.
2. After the intervention of the ACS Sir, a joint meeting of both departments was conducted by the DM, Jhansi.
3. Thereafter, a joint site inspection was carried out by the Chief Engineer (CE), UPJN, and CE, PWD.
4. It was mutually agreed that the pipeline-laying work would be carried out by PWD under the supervision of UPJN and the firm.
5. Accordingly, PWD started the work on 01.05.2026.
6. The work was stopped due to the rainy season and was not resumed thereafter.
7. Following the intervention of the MD sir - UPJN (R), the DM - Jhansi, convened a meeting with both departments, and the work was resumed on 01.09.2026. But, once again stopped by PWD from 20.09.2026.
8. In the meeting convened by the DM, Jhansi, on 23.09.2026, DM directed PWD to complete remaining works immediately. PWD stated that the remaining works will be completed by 15.10.2026.
9. However, thereafter, the work has not been resumed and no work is in progress at present. |
| 23 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Arjar |
424226 |
Arjar |
Road Widening[PWD] |
12-Jan-2024 |
|
PWD has damaged the pipeline from last 2.5 years. As per the instruction of ACS sir, joint meeting was conducted by DM Jhansi. There after joint site inspection was conducted by CE- UPJN and CE- PWD and there after work has been started by PWD on 01-05-2026. However, the work has been stopped due to rainy season for two months. Due to the intervention of MD-UPJN and DM Jhansi on 01-09-2026 work re-started. The completion date will be finalised during the meeting called by DM Jhansi on 23-09-2026. |
| 24 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Arjar |
424226 |
Arjar |
Road Widening[PWD] |
12-Jan-2024 |
|
PWD has damaged the pipeline, and the issue has remained unresolved for the last 2.5 years. After the intervention of the ACS Sir, a joint meeting of both departments was conducted by the DM, Jhansi.
Thereafter, a joint site inspection was carried out by the Chief Engineer (CE), UPJN, and CE, PWD. It was mutually agreed that the pipeline-laying work would be carried out by PWD under the supervision of UPJN and the firm.
Accordingly, PWD started the work on 01.05.2026. However, the work was stopped due to the rainy season and was not resumed thereafter.
Following the intervention of the MD sir - UPJN (R), the DM - Jhansi, convened a meeting with both departments, and the work was resumed on 01.09.2026. The work is currently in progress.
The completion date will be finalized during the meeting convened by the DM, Jhansi, on 23.09.2026. |
| 25 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Arjar |
424226 |
Arjar |
Road Widening[PWD] |
12-Jan-2024 |
31-Oct-2026 |
PWD has damaged the pipeline, and the issue has remained unresolved for the last 2.5 years. After the intervention of the ACS Sir, a joint meeting of both departments was conducted by the DM, Jhansi. Thereafter, a joint site inspection was carried out by the Chief Engineer (CE), UPJN, and CE, PWD. It was mutually agreed that the pipeline-laying work would be carried out by PWD under the supervision of UPJN and the firm. Accordingly, PWD started the work on 01.05.2026. However, the work was stopped due to the rainy season and was not resumed thereafter. Following the intervention of the MD sir - UPJN (R), the DM - Jhansi, convened a meeting with both departments, and the work was resumed on 01.09.2026. The work is currently in progress. The completion date will be finalized during the meeting convened by the DM, Jhansi, on 23.09.2026.In this meeting DM has directed to PWD remaining works would be completed as soon as possible.In complaince PWD stated that the remaining works will take 1 month for complaince . |
| 26 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Arjar |
424226 |
Arjar |
Road Widening[PWD] |
12-Jan-2024 |
|
1. PWD has damaged the pipe line during road widening in 2024. and the issue has remained unresolved.
2. After the intervention of the ACS Sir, a joint meeting of both departments was conducted by the DM, Jhansi.
3. Thereafter, a joint site inspection was carried out by the Chief Engineer (CE), UPJN, and CE, PWD.
4. It was mutually agreed that the pipeline-laying work would be carried out by PWD under the supervision of UPJN and the firm.
5. Accordingly, PWD started the work on 01.05.2026.
6. The work was stopped due to the rainy season and was not resumed thereafter.
7. Following the intervention of the MD sir - UPJN (R), the DM - Jhansi, convened a meeting with both departments, and the work was resumed on 01.09.2026. But, once again stopped by PWD from 20.09.2026.
8. In the meeting convened by the DM, Jhansi, on 23.09.2026, DM directed PWD to complete remaining works immediately. PWD stated that the remaining works will be completed by 15.10.2026.
9. However, thereafter, the work has not been resumed and no work is in progress at present. |
| 27 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Arjar |
424226 |
Arjar |
Road Widening[PWD] |
12-Jan-2024 |
|
Pwd has damaged the pipeline from last 1.5 years and not repaired it till now. |
| 28 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Arjar |
424227 |
Rampura |
Road Widening[PWD] |
16-Jan-2024 |
|
Pwd has damaged the pipeline from last 1.5 years and not repaired it till now |
| 29 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Arjar |
424227 |
Rampura |
Road Widening[PWD] |
16-Jan-2024 |
|
PWD has damaged the pipeline from last 2.5 years. As per the instruction of ACS sir, joint meeting was conducted by DM Jhansi. There after joint site inspection was conducted by CE- UPJN and CE- PWD and there after work has been started by PWD on 01-05-2026. However, the work has been stopped due to rainy season for two months. Due to the intervention of MD-UPJN and DM Jhansi on 01-09-2026 work re-started. Partial water supply has been started at this village. The completion date will be finalised during the meeting called by DM Jhansi on 23-09-2026. |
| 30 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Arjar |
424227 |
Rampura |
Road Widening[PWD] |
16-Jan-2024 |
|
PWD has damaged the pipeline, and the issue has remained unresolved for the last 2.5 years. After the intervention of the ACS Sir, a joint meeting of both departments was conducted by the DM, Jhansi.
Thereafter, a joint site inspection was carried out by the Chief Engineer (CE), UPJN, and CE, PWD. It was mutually agreed that the pipeline-laying work would be carried out by PWD under the supervision of UPJN and the firm.
Accordingly, PWD started the work on 01.05.2026. However, the work was stopped due to the rainy season and was not resumed thereafter.
Following the intervention of the MD sir - UPJN (R), the DM - Jhansi, convened a meeting with both departments, and the work was resumed on 01.09.2026. Water supply has been started partially and the work is currently in progress.
The completion date will be finalized during the meeting convened by the DM, Jhansi, on 23.09.2026. |
| 31 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Arjar |
424227 |
Rampura |
Road Widening[PWD] |
16-Jan-2024 |
31-Oct-2026 |
PWD has damaged the pipeline, and the issue has remained unresolved for the last 2.5 years. After the intervention of the ACS Sir, a joint meeting of both departments was conducted by the DM, Jhansi. Thereafter, a joint site inspection was carried out by the Chief Engineer (CE), UPJN, and CE, PWD. It was mutually agreed that the pipeline-laying work would be carried out by PWD under the supervision of UPJN and the firm. Accordingly, PWD started the work on 01.05.2026. However, the work was stopped due to the rainy season and was not resumed thereafter. Following the intervention of the MD sir - UPJN (R), the DM - Jhansi, convened a meeting with both departments, and the work was resumed on 01.09.2026. The work is currently in progress. The completion date will be finalized during the meeting convened by the DM, Jhansi, on 23.09.2026.In this meeting DM has directed to PWD remaining works would be completed as soon as possible.In complaince PWD stated that the remaining works will take 1 month for complaince ..During site visit it is observe that the damaged pipeline in Village Rampura has been repaired by the PWD. 3 inter connection are left due to which 0nly partially water supply are resume.If this inter connection has been made than will get proper water supply in complete village. However, the PWD has stopped the work since 20 September, due to which the interconnection work of the branch pipeline remains pending and 100% water supply in the village could not be started. |
| 32 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Arjar |
424227 |
Rampura |
Road Widening[PWD] |
16-Jan-2024 |
|
1. PWD has damaged the pipe line during road widening in 2024. and the issue has remained unresolved.
2. After the intervention of the ACS Sir, a joint meeting of both departments was conducted by the DM, Jhansi.
3. Thereafter, a joint site inspection was carried out by the Chief Engineer (CE), UPJN, and CE, PWD.
4. It was mutually agreed that the pipeline-laying work would be carried out by PWD under the supervision of UPJN and the firm.
5. Accordingly, PWD started the work on 01.05.2026.
6. The work was stopped due to the rainy season and was not resumed thereafter.
7. Following the intervention of the MD sir - UPJN (R), the DM - Jhansi, convened a meeting with both departments, and the work was resumed on 01.09.2026. But, once again stopped by PWD from 20.09.2026.
8. During site visit it is observed that the damaged pipeline in Village Rampura has been repaired by the PWD.
9. Three inter connections are left due to which 0nly partial water supply was resumed. Water supply in entire village can be resumed once the interconnections are made.
10. However, the PWD has stopped the work since 20 September, due to which the interconnection work of the branch pipeline remains pending and 100% water supply in the village could not be restored.
11. In the meeting convened by the DM, Jhansi, on 23.09.2026, DM directed PWD to complete remaining works immediately. PWD stated that the remaining works will be completed by 15.10.2026.
12. However, thereafter, the work has not been resumed and no work is in progress at present. |
| 33 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Ninaura |
424230 |
Ninaura |
Road Widening[PWD] |
19-Sep-2026 |
|
Pwd has damaged the pipeline from last 1.5 years and still not repaired it till now. |
| 34 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Arjar |
424227 |
Rampura |
Road Widening[PWD] |
19-Sep-2026 |
|
PWD-damaged pipeline has remained unresolved for the last 1.5 years. Repair work is now in progress. DM meeting is scheduled on 23-09-2026 with PWD officers for review. |
| 35 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Arjar |
424226 |
Arjar |
Road Widening[PWD] |
19-Sep-2026 |
|
PWD-damaged pipeline has remained unresolved for the last 1.5 years. Repair work is now in progress. DM meeting is scheduled on 23-09-2026 with PWD officers for review. |