| 1 |
20013640 |
Dakkhin Gaon Water Supply Scheme |
Amethi |
Shahgarh |
Dakkhin Gaon |
439577 |
Pachhela |
Road Widening[NHAI] |
10-Jul-2026 |
30-Sep-2026 |
<p>On 17/11/2026, a meeting was held under the chairmanship of the DM, Amethi with officials from Jal Nigam (Gramin) Amethi, PWD, and PWD (NH), along with the executing agencies, regarding the water supply disruption caused by pipeline damage during road widening. It was decided that all disruptions will be resolved and water supply restored by December 20. The executing agencies responsible for the disruption have also agreed to complete the work by December 20.</p> |