Sr.No.         District               City/Town       Name of Sewerage Project Scheeme Type Mode of Project AA&ES and date No. of STP STP Capacity No.Of Drains Agency Name Agreement Cost
Date of Start
Date of Comp. As per Agreement
Revised Date
Current Progress Component Wise Physical progress
Date of updation
Remark
Reason for Delay
Action taken for delay
Tentative date for inauguration
Tentative Zero Discharge Date
Date of Sanction Sanction cost work Cost Centage O & M Cost Physical Progress(%) Financial Progress(Cr)
Work Component
No Of Component Capacity/Length/No Physical Progress(%) Photos
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 34 35
Total -- -- -- 5435.40 2663.05 180.64 2490.42 35 1089.10 180 -- 3562.11 -- -- -- -- -- -- -- -- +0
30.96
-- -- -- -- -- -- --
1 Agra Agra Agra Sewerage Scheme( Interception & diversion and STP works) NGP2-EAP HAM 06-May-2020 842.25 371.29 25.40 445.56 13 177.60 26 M/s AWWMPL Pvt Ltd 582.84 05-Apr-2023 04-Apr-2025
04-Apr-2025
31-Dec-2025
+0.06
79.90
+0.00
332.00
Effluent Disposal Line (km.) 2 2.01 92.50 12 24-Feb-2026
  • Component wise progress of Agra (HAM) 100 MLD STP- 68%, WIP 35 MLD STP- 76.2, WIP 31 MLD STP- 76.48%, WIP MPS 03 Nos.- 73%, WIP Rising Main 9.55 Km- 55%%, WIP Gravity Sewer 2.55 Km- 80%, WIP DSTP 10 Nos.- 5%, WIP Note- 1st Stage permission is granted for 07 Nos. DSTP Forest Land and 2nd stage permission is under process
  • As per pervious meeting discussion, In order to complete the remaining works of 31 MLD and 35 MLD STP and make them operational as per the prescribed timeline, Direction has been given to firm to complete the works as early as possible by increasing manpower.
  • As per pervious meeting discussion, In order to 07 Nos. DSTP forest clearance , Land Gazette notification meeting has been conducted on 02.05.2025 and soon gazette notification will be published and after that stage 2 permission will be applied
NOC of land for 7 Nos DSTP, Road cutting permission for laying of rising main , 1st Stage Permission was granted from forest department and 2nd stage permission is under process. A request was made by District Magistrate proposal sent to Revenue department UP Lucknow for 1 No. DSTP Indira Memorial. In current laying of rising main and intercepting sewer line permission was granted by district administration and work is under progress. MPS Nagla Buri public hindrance was resolved work is under progress. 01-Nov-2026 01-Sep-2026
Intercepting Sewer (km) 3 1.94 82.00 4
Interception And Diversion 1 22.00 0.00 0
MPS (MLD) 3 373.50 82.67 45
Rising main (mtr.) 3 8970.00 76.67 26
STP (MLD) 13 177.60 26.94 103
2 Mathura Chhata Chhata Town Sewerage Scheme (I&D and STP works), District Mathura NGP DBOT 25-Oct-2022 56.15 34.52 2.23 19.40 1 6.00 14 M/s Shailesh Kumar J.V. 48.97 12-Nov-2024 11-Aug-2026 +0.53
10.50
+0.00
1.65
Ancilliary works(Admin building,staff quarter ,roa 1 1.00 8.00 0 24-Feb-2026
  • STP site is flooded due to overflow from Bahrauli branch drain, (situated near to the site) from 1 month. The current water level at STP site is higher to the HFL, provided by irrigation department. At this situation all works are heavily affected. Not only in present this kind of situation during monsoon will affect the operation and maintenance services in later too. Due to the current scenario of site, we have sent a letter to SDM, Chhata, requesting a new land for construction of STP in this project with all requisite details of the scenario of original project site.
  • Construction of HTS and staff quarter building is in progress at MPS.
  • Project is slightly delayed due to problem of water logging at STP Site as PWD, Mathura was constructing a culvert on Kosi Drain and due to diversion of drain the water of kosi drain got obstructed. The STP site is located near to the branch drain of kosi drain at upstream side which got over flowed and leading to water logging at STP Site.This hindrance cleared in march 2025 after that work was resumed.
  • Date of Start 12.11.2024 has been given to the firm.
  • Survey and soil investigation has completed by firm.
  • BEP of STP has been approved.
  • Boundary wall construction work is going on at site.
Project is slightly delayed due to problem of water logging at STP Site as PWD, Mathura was constructing a culvert on Kosi Drain and due to diversion of drain the water of kosi drain got obstructed. The STP site is located near to the branch drain of kosi drain at upstream side which got over flowed and leading to water logging at STP Site. Communication has been done to PWD and Irrigation Department for the problem of water logging at site. Additionally firm has been instructed to take preventive measures and initiate the work. Now the Piling and associated work has been commenced at site for SBR basin. 12-Aug-2026 12-Aug-2026
I/C Sewer line (Mtr.) 1 2170.00 0.00 0
Interception And Diversion 1 11.00 0.00 0
MPS (MLD) 1 6.00 20.00 10
Rising Main (Meter) 1 5500.00 0.00 0
STP (MLD) 1 6.00 9.00 4
3 Rae Bareli DPR OF 08 KLD Fecal Sludge Treatment Plant At Dalmau Raibareli NMCG DBOT 28-Aug-2024 4.40 3.01 0.18 1.21 0 0.00 0 M/s Aastha Enviro Engineers Pvt Ltd 3.00 06-Feb-2026 05-Nov-2026 +0.00
0.00
+0.00
0.00
FSTP(KLD) 1 8.00 0.00 0
  • Bid Document uploaded at e-tender portal on dt. 27.06.2025.
  • Pre-bid Meeting dt. 04.07.2025 at 12:00 PM.
  • Pre-bid reply sent to NMCG for review and approval on dt. 07.07.2025.
  • NMCG sent final pre-bid replies on dt. 05.08.2025.
  • Final pre-bid replies uploaded on e-tender portal on dt. 07.08.2025 Bid Submission date 22.08.2025.
  • Technical Bid open on dt. 22.08.2025.
  • TBER sent to NMCG for review and approval.
  • NOC received from NMCG on dt. 03.10.2025.
  • Financial bid open on dt. 10.10.2025. Financial Evaluation work is in progress.
  • FBER sent to NMCG for review and approval on dt. 01.12.2025.
  • NOC received from NMCG of FBER on dt. 19.12.2025
  • LOA issued to Firm M/s Aastha Enviro Engineers Pvt. Ltd. on dt. 30.12.2025.
  • Date of start given to Firm M/s Aastha Enviro Engineers Pvt. Ltd. on dt. 06.02.2026.
05-Dec-2026 05-Dec-2026
4 Pratapgarh Faecal Sludge Management for Pollution abatement of river Ganga at Manikpur, Pratapgarh Non EAP DBOT 22-Jan-2025 8.56 5.73 0.19 1.90 0 0.00 0 0.00 +1.00
1.00
+0.00
0.00
Co-Treatment Facility(KLD) 1 15.00 1.00 0 24-Feb-2026
  • Bid Document submitted to NMCG, New Delhi on 01.04.2025 for approval.
  • NIT has been floated on E-Tender portal on dated 02.05.2025. Last date of bid submission is 30.06.2025.
  • Pre Bid Meeting held on Dated 15.05.2025
  • Pre Bid Queries sent to NMCG, New Delhi on dated 21.05.2025, observation were made by NMCG, New Delhi on Dated 03.06.2025. Compliance of the same sent on dated 09.06.2025 and Approval by NMCG, New Delhi on Dated 12.06.2025
  • Zonal Committee meeting held on 07.08.2025 and Head Quarter meeting held on 08.08.2025 for technical evaluation of bid.
  • Letter has been sent by Chief Engineer (Ganga), UPJN (Rural), Lucknow on dated 27.08.2025 to ED (Project) NMCG New Delhi for approval of Technical Evaluation.
  • NMCG New Delhi has given approval for opening of financial bid vide letter no. Pr-12012/8/2022-TECH1 NMCG, dated 13.09.2025 (after getting confirmation from M/s Aastha ).
  • Financial Bid has been opened on date 08.10.2025.
  • Head Quarter meeting held on 04.11.2025 for Financial evaluation of bid.
  • Letter has been sent by Chief Engineer (Ganga), UPJN (Rural), Lucknow on dated 20.11.2025 to ED (Project) NMCG New Delhi for approval of Financial Evaluation.
  • NMCG New Delhi has given approval for issuance of LOA to the L1 Firm M/s Aastha
  • LOA has been issued to firm on dated 23.12.2025
  • Date of start has been issued to firm on dated 04.02.2026. Date of start 05.02.2026 and Date of Completion 04.11.2026
  • Survey, Design and Site cleaning and leveling work is under progress.
01-Jan-1900 01-Jan-1900
5 Bulandshahr Gulaothi I&D works NMCG DBOT 28-Aug-2024 50.98 17.13 1.37 13.20 1 10.00 1 M/s SKC Technocrat Pvt. Ltd (Formerly M/s Satish Kumar & Co.) & M/s Malvika Technical Services (JV) 51.19 01-Dec-2025 31-May-2027 +0.00
3.00
+1.04
1.04
Interception And Diversion 1 1.00 0.00 0 24-Feb-2026
  • AA&ES issued on Dt 28.08.2024
  • NIT issued by SE, Meerut vide letter no. 257/731/15 Dt 08.11.2024
  • LOA & Date of start is given on 26.11.2025. Date of start is 01.12.2025 & Date of completion of work is 31.05.2027 issued to M/s SKC Technocrat Private Limited- M/s Malvika Technical Services (JV), B-29, RDC, Raj Nagar, Ghaziabad- 201002
  • Soil Testing Complete. Boundary Wall work is in progress.
  • BEP submitted by the firm on Dated 03.02.2026. Some Observation were found in the examination of BEP, after which BEP was returned to the firm on 08.02.2026.
  • The land purchase proposal has been Sanctioned and GO issued. The funds Released to ULB Gulaothi. Land Registry work is completed. ULB handed over the land to U.P. Jal Nigam for work on Dated 20.12.2025.
- 31-May-2027 31-May-2027
STP (MLD) 1 10.00 0.00 0
6 Mathura Vrindavan I&D and 13 MLD STP works at Vrindavan City NGP DBOT 25-Oct-2022 77.70 39.90 2.56 35.24 1 13.00 2 M/s SIMA -G D- N.P. (JV) 65.86 11-Jun-2024 10-Mar-2026 +0.57
88.93
+0.00
24.07
Ancilliary works(Admin building,staff quarter ,roa 1 1.00 94.00 4 24-Feb-2026
  • Kalideh MPS rising main works has been done.
  • STP site is water logged from 10.08.2025, work is affected due to this
  • STP site had been water logged from 10.08.2025 to 18.09.2025, due to the high flood of Yamuna. After receding of water construction work is in progress along with corrective works due to the damage by flood at site.
  • Work is going in SBR basin, CCT, Admin building, Pannel room, SHU and in MPS units.
  • LOA issued to firm on dated 15.03.2024. Effective Date of start for the work is 11.06.2024.Work is in progress.
Initially preliminary work at Site got hindered due to start of monsoon just after the date of start of the project. Firm has started the work after the monsoon and currently the work is being going on almost on all fronts by the firm. The progress is being regularly expedited by firm to complete the work on scheduled date. - 11-Mar-2026 11-Mar-2026
Interception And Diversion 1 2.00 70.00 0
MPS (MLD) 1 6.00 82.00 8
Online Monitoring/LCS/MCS for proposed STPs and Ex 1 1.00 0.00 0
Rising main (mtr.) 1 3700.00 94.00 0
STP (MLD) 1 13.00 96.00 29
Treated water sump and associated works 1 1.00 95.00 0
Upgradation of MPS 1 1.00 60.00 0
7 Shamli Banat I&D and STP Work in Banat, Shamli NGP DBOT 25-May-2023 48.71 24.93 1.58 22.20 1 5.00 3 M/s R K Engineers Sales Ltd 37.92 14-Oct-2024 13-Apr-2026 +2.00
48.40
+0.00
4.02
Co-treatment Unit for Fecal Sludge (KLD) 1 5.00 3.00 0 23-Feb-2026
  • Contract Agreement is signed on 08.10.2024 and Date of Start 14-10-2024 & Date of Completion 13-01-2026
  • Survey and Soil investigation work completed
  • BEP, Layout and HFD approved for 05 MLD STP.
  • Gate Schedule approved
  • GAD, Structural design and drawing of CCT with Tonner Room & HT Substation approved
  • GAD, Structural Design and Dwg. for SBR and Boundary wall approved.
  • Approach Road and boundary wall work in progress
  • GAD for Sludge Handling Unit Submitted, which are clear for Vetting & Structural Design.
  • Project is 4 months behind schedule.
  • Delay in design/drawing submission by Contractor.
  • Contractor need to increase expedite the progress of work and submission of design/drawings.
  • GAD, Structural Design and Dwg. for SHU approved
  • GAD, Structural design and drawing of I&D Structure approved
  • GAD and Data Sheet of Diffuser and decanter approved
  • BEP, P&ID of MPS approved
  • GAD, Structural design and drawing of PTU Structure approved
  • GAD, Structural design and drawing of CCT, HT Substation Building and MPS which are clear for Vetting.
  • Structural Design and Dwg. for MPS approved
  • Data Sheet, QAP, Curves etc. of Turbo Blower, Centrifuge approved
Firm delayed submission of Design and drawing Liquidity Damage (L.D.) imposed on firm for delay. 24-Apr-2026 14-Apr-2026
Effluent Disposal Line (km.) 1 0.60 0.00 0
Interception And Diversion 1 2.00 10.00 0
MPS (MLD) 1 6.00 60.00 8
Power Connection 1 1.00 0.00 0
Rising main (mtr.) 1 50.00 0.00 0
Sewer Line (km.) 1 0.60 0.00 0
STP (MLD) 1 5.00 38.00 21
8 Shamli Bantikhera Banat I&D and STP Work in Bantikhera and Babri village, Shamli NGP DBOT 25-May-2023 55.47 29.41 1.84 24.22 1 5.00 1 M/s R K Engineers Sales Ltd 41.91 14-Oct-2024 13-Apr-2026 +0.30
7.60
+0.00
1.38
Co-treatment Unit for Fecal Sludge (KLD) 1 5.00 3.00 0 23-Feb-2026
  • Contract Agreement is signed on 08.10.2024 and Date of Start 14-10-2024 & Date of Completion 13-01-2026
  • Survey and Soil investigation work completed
  • BEP, Layout and HFD approved for 05 MLD STP.
  • Work halted due to unresolved land dispute.
  • Project is 7 months behind schedule.
  • GAD of SBR is Clear for Vetting and Structural design
  • Date Sheet, QAP, Curves etc. of Turbo Blower, Centrifuge approved
  • Gate Schedule approved
  • GAD, Structural design & Dwg. of PTU approved
Due to land dispute Letters has been written to the District Administration requesting their intervention to resolve the dispute with the nearby farmers. 24-Apr-2026 14-Apr-2026
Effluent Disposal Line (km.) 1 0.40 0.00 0
Interception And Diversion 1 4.00 0.00 0
MPS (MLD) 1 6.00 0.00 0
Power Connection 1 1.00 0.00 0
Rising main (mtr.) 1 50.00 0.00 0
Sewer Line (km.) 1 2.00 0.00 0
STP (MLD) 1 5.00 9.00 14
9 Saharanpur I&D and STP Work in Deobandh NGP DBOT 25-Jul-2024 134.71 67.42 4.46 62.83 1 20.00 4 M/s 21st Century Enviro Engineers Pvt. Ltd. -M/s Sattva Engineering Const. Ltd. JV 95.25 09-Feb-2026 08-Jul-2027 +0.00
0.00
+0.00
0.00
MPS (MLD) 1 28.00 0.00 0 23-Feb-2026
  • Technical bid evaluation sheet and document send to NMCG on 28.04.2025
  • NOC on pre- Bid Documents recieved 0n 18.12.2024
  • Technical Bid opened on 25.01.2025
  • Letter to lowest bidder regarding power consumption written on dated 14.08.2025 last date for reply is 20.08.2025
  • Reply received on dated 20.08.2025
  • LOA issued to M/s 21st Century Enviro Engineers Pvt. Ltd. -M/s Sattva Engineering Const. Ltd. JV. on dt. 14.11.2025
  • Financial bid send to NMCG on dated 04.09.2025
  • Approval recieved on 16.09.2025
  • AA&ES recieved on 25.07.2024.
  • Approval on Technical bid from NMCG recieved on 29.07.2025
  • Financial bid opened on 07-08-2025 and financial evaluation under process.
  • Draft bid document and NIT sent to NMCG on 05.08.2024 for approval.
  • Comments on draft Bid Documents recieved on 17.10.2024
  • NIT published on 24-10-2024
  • Pre-bid meeting held on 07.11.2024
  • Draft pre-bid reply send to NMCG 24.11.2024
- - 08-Nov-2027 08-Nov-2027
Power Connection 1 1.00 0.00 0
Rising main (mtr.) 1 50.00 0.00 0
Sewer Line (km.) 1 3.83 0.00 0
STP (MLD) 1 20.00 0.00 4
10 Shamli Shamli I&D and STP Work in Shamli NGP DBOT 25-May-2023 206.02 103.19 6.66 96.17 1 40.00 1 M/s R.K. Engineers Sales Ltd.-M/s Anand Constrwell Pvt. Ldt. (JV) 120.92 14-Oct-2024 13-Apr-2026 +2.00
50.80
+0.00
15.44
Co-treatment Unit for Fecal Sludge (KLD) 1 20.00 3.00 0 23-Feb-2026
  • Primary Clariflocculator GAD Submitted, which clear for Vetting & Structural Design.
  • CCT GAD Submitted which clear for Vetting & Structural Design.
  • BEP, P&ID, HFD of MPS approved
  • Data Sheet, QAP, Curves etc. of Turbo Blower, Centrifuge approved
  • Gate Schedule & Electrical load list approved
  • GAD, Structural Design and Dwg. of CCT/Toner Room & Fiber Disk Filter approved
  • GAD, Structural Design and Dwg. for MPS approved
  • Contract Agreement is signed on 08.10.2024 and Date of Start 14-10-2024 & Date of Completion 13-01-2026
  • Approach Road and Boundary wall work in progress
  • BEP, Layout and HFD approved for 40 MLD STP.
  • GAD, Structural Design and Dwg. for SBR and Boundary wall approved.
  • GAD for Admin Building and Sludge Handling and Dewatering Building Submitted, which clear for Vetting & Structural Design.
  • CCT and I&D GAD Submitted, which clear for Vetting & Structural Design.
  • Project is 4 months behind schedule.
  • Delay in design/drawing submission by Contractor.
  • Contractor need to increase expedite the progress of work and submission of design/drawings.
  • GAD, Structural Design and Dwg. for SHU approved
  • GAD, Structural Design and Dwg. of I&D Structure approved
  • GAD and Data sheet of Decanter and diffuser approved
  • GAD, Structural Design and Dwg. for Admin. Building & Lab approved
  • GAD, Structural Design and Dwg. of Staff Quarter approved
Firm delayed submission of Design and drawing Liquidity Damage (L.D.) imposed on firm for delay. 24-Apr-2026 14-Apr-2026
Effluent Disposal Line (km.) 1 0.10 0.00 0
Interception And Diversion 1 1.00 5.00 9
MPS (MLD) 1 48.00 21.00 8
Power Connection 1 1.00 0.00 0
Rising main (mtr.) 1 100.00 0.00 7
Sewer Line (km.) 1 0.10 0.00 0
STP (MLD) 1 40.00 41.20 26
11 Shamli Thanabhawan I&D and STP Work in Thanabhawan, Shamli NGP DBOT 25-May-2023 97.19 55.63 3.50 38.06 1 10.00 5 M/s R K Engineers Sales Ltd 63.72 14-Oct-2024 13-Apr-2026 +2.00
47.68
+0.00
6.32
Co-treatment Unit for Fecal Sludge (KLD) 1 10.00 0.00 0 23-Feb-2026
  • GAD, Structural Design and Dwg. for SBR and Boundary wall approved.
  • GAD for Sludge Handling Unit Submitted, which are clear for Vetting & Structural Design.
  • CCT GAD were Submitted, which clear for Vetting & Structural Design.
  • Boundary Wall work in progress
  • Project is 4 months behind schedule.
  • Delay in design/drawing submission by Contractor.
  • Contractor need to increase expedite the progress of work and submission of design/drawings.
  • GAD, Structural Design and Dwg. for SHU approved
  • GAD and Data Sheet of Diffuser and decanter approved
  • BEP, P&ID of MPS approved
  • GAD of MPS submitted which is clear for vetting
  • GAD, Structural Design and Dwg. for PTU and CCT Submitted which are clear for Vetting
  • Structural Design and Dwg. for MPS submitted which is clear for Vetting
  • GAD of Fiber Disk filter submitted which is clear for vetting
  • Data Sheet, QAP, Curves etc. of Turbo Blower, Centrifuge approved
  • Gate Schedule & Electrical load list approved
  • Structural Design and Dwg. of PTU, Fiber Disk Filter, I&D and Sewer Network approved
  • Structural Design and Dwg. for MPS approved
  • Structural Design and Dwg. for CCT with Tonner Room approved
  • Contract Agreement is signed on 08.10.2024 and Date of Start 14-10-2024 & Date of Completion 13-01-2026
  • Survey and Soil investigation work completed
  • Approach Road work in progress
  • BEP, Layout and HFD approved for 10 MLD STP.
Firm delayed submission of Design and drawing Liquidity Damage (L.D.) imposed on firm for delay. 24-Apr-2026 14-Apr-2026
Interception And Diversion 1 3.00 7.00 0
MPS (MLD) 1 13.00 15.00 0
Power Connection 1 1.00 0.00 0
Rising main (mtr.) 1 60.00 0.00 0
Sewer Line (km.) 1 5.60 6.00 0
STP (MLD) 1 10.00 41.00 12
12 Hapur Hapur I&D and STP works at District-Hapur NGP DBOT 19-Sep-2023 49.06 22.85 1.42 24.79 1 6.00 1 M/s SKC Technocrat Pvt. Ltd (Formerly M/s Satish Kumar & Co.) & M/s. Geo Miller & Co. Pvt. Ltd. (JV) 39.28 08-Nov-2024 07-Feb-2026 +5.00
25.00
+3.01
4.73
Drains 1 1.00 0.00 0 24-Feb-2026
  • Date of start is given on 08.11.24. Date of completion of work is 05.02.2026 to M/s SKC Technocrat Pvt. Ltd (Formerly M/s Satish Kumar & Co.) & M/s. Geo Miller & Co. Pvt. Ltd. (JV), Reg. Office B-29, IIIrd Floor, RDC Rajnagar, Ghaziabad - 201013. AGREEMENT cost of project is Rs. 39,28,13,617.00.
  • Soil Testing Completed. Boundary Wall work is in progress.
  • Land Issue Resolved in March 2025.
  • The amount of mobilization advance has been claimed by the firm.
  • BEP and GAD sent for vetting to IIT BHU VARANASI on 19.06.25
  • LD of Rs. 28.00 Lac has been imposed on firm for delay of work, as per contract agreement.
  • Revised vetted BEP Civil/Mechanical GA & R/F of MPS, SHU and SBR has been submitted by the firm on Dt 25.10.2025 and approved by the Department except Civil GA and R/F of SBR.
Firm delayed submission of Design and drawing. LD has been imposed vide letter no- 422/790/33 Dt 22.09.2025 due to delay in approval of Design/Drawing. 07-Feb-2026 07-Feb-2026
MPS (MLD) 1 8.00 58.00 8
Others 1 1.00 62.00 4
STP (MLD) 1 6.00 25.00 8
13 Hathras Hathras I&D and STP works at Hathras Town NGP DBOT 30-Jan-2023 128.91 70.48 4.55 53.88 1 24.00 10 M/s Neercare India pvt KLtd JV M/s EMIT Group India Pvt Ltd JV EMS Ltd 119.05 06-Sep-2024 05-Jun-2026 +3.95
38.79
+0.00
11.05
Admin Block 1 1.00 12.35 0 24-Feb-2026
  • Survey and soil investigation has been completed by firm
  • Date of start is 06.09.2024 and date of completion is 05.06.2024. Survey work is going on.
  • Project was delayed as the land for STP was handed over in March 2025 by Nagar Palika Parishad Hathras. After that BEP is approved and structural drawings of SBR also vetted by IIT and at present excavation for SBR is in progress
Land issued by NPP Project Manager personally contacted the District Magistrate and requested to remove the potato crop, on which the District Magistrate talked to the Executive Officer over telephone and directed to remove the potato crop within 7 working days. As per the instructions of the District Magistrate, the construction work of STP could be started in the month of March 2025 after removing the potato crop from the land provided by the Executive Officer Municipal Council Hathras 30-Nov-2026 05-Jun-2026
Boundary wall (mtr.) 1 800.00 0.00 0
Intercepting Sewer (km) 1 5.67 16.50 0
MPS (MLD) 1 54.00 72.00 4
Nala Tapping Arrangement ( No.) 1 8.00 0.00 0
Rising main (mtr.) 1 0.13 0.00 0
Staff Quarter type 2 1 1.00 0.00 0
STP (MLD) 1 24.00 42.00 17
14 Mathura Kosi Kalan I&D and STP works at Kosi Kalan Town, District Mathura NGP DBOT 25-Oct-2022 66.59 31.24 2.03 33.32 1 12.00 1 M/s R K Engineers Sales Ltd 53.60 16-Oct-2024 15-Jul-2026 +5.22
35.50
+0.00
1.53
Ancilliary works(Admin building,staff quarter ,roa 1 1.00 25.00 0 24-Feb-2026
  • Continous instruction has been given to firm for expediting the work.
  • BEP of STP has been approved.
  • Boundary wall construction work is going on at site.
  • Preparation for PCC work of SBR basin is in progress, hindered due to rain at site.
  • LOA has been issued on date 18.06.2024 and Date of start has been given 16.10.2024 to the firm. Survey work is going on
  • Survey and soil investigation has been done by firm.
  • Ground improvement work of SBR basin is completed, PCC work is in progress.
Firm has taken additional time in initial document submission and ULB's continuous waste disposal at project site also hindered the work. Letter had been written to ULB to stop waste disposal at site. It was stopped and site was cleared for the work. Additionally notices/letters has been written to the firm for expediting the progress. Now the firm has been expedited the work and SBR basin work is in progress. 16-Jul-2026 16-Jul-2026
Intercepting Sewer (km) 1 0.03 0.00 0
MPS (MLD) 1 12.00 27.00 0
Nala Tapping Arrangement ( No.) 1 1.00 0.00 0
Rising main (mtr.) 1 100.00 0.00 0
STP (MLD) 1 12.00 41.00 12
15 Meerut Meerut I&D and STP works at Meerut NGP2-EAP HAM 06-May-2020 690.71 363.78 26.31 280.19 1 220.00 2 M/s. Meerut STP Pvt. Ltd. 369.74 11-Nov-2024 10-Nov-2026 +0.34
47.07
+0.00
110.57
Interception And Diversion 1 2.00 10.00 0 23-Feb-2026
  • QAP, Date Sheet and GAD of Decanter, Diffuser, Vortex Grit Chamber, Turbo Air Blower, Fine & Coarse Screens, Chlorination System & Leak Absorption System, RAS SAS, RSTP Pumps, Belt Filter Press, Gravity Belt Thickener, Screw Pumps approved.
  • QAP, Date Sheet and GAD of Gas Flare System, under re-submission., RCC drawing & design Calculations of Odean Nala I&D under re-submission.
  • GAD, Blower & Panel Building, SBR piping, HT panel & workshop, Security HT Panel-2 Metering Room, Electrical BEP, pending with Concessionaire. GAD of Odean Nala & Abu Nala-2 I&Ds under review with IIT Roorkee., RCC of Compound walls approved.
  • . Payment for1st and 2nd MS have been released
  • BEP, Layout and HFD approved for 220 MLD STP, 2 I&D’s & MPS, BEP of Treated Effluent Pipeline from Lohia Nagar STP to Outfall pending with Concessionaire, BEP of EPS and Pipeline pending with Concessionaire. GAD, Structural Design and Dwg. for Admin Building, SBR, CCT, Tonner Room approved QAP, Date Sheet and GAD of Decanter, Diffuser approved, QAP, Date Sheet and GAD of Air Blowers under review., Vortex Grit Remover approved by PE. GAD of Primary Clarifier approved by UPJN. , QAP, Date Sheet and GAD of Chlorination System pending with Concessionaire. QAP of Filter Belt Press pending with Concessionaire., Revised QAP of Pumps to be submitted by Concessionaire. Revised GAD of MPS pending with Concessionaire.
  • Work in progress at only 1 front of STP, Concessionaire need to open multiple working fronts. Inadequate Manpower deployment at site, Manpower deployment to be increased.
  • ESIA/ ESMP under review with World Bank
  • BEP of EPS and Pipeline works has been recommended by PE.
The 3rd and 4th milestones are delayed as the design and drawings have not been submitted by the firm. Due to this work not having started on different fronts. 21-Feb-2027 11-Feb-2027
MPS 1 1.00 37.00 6
Power Connection 1 1.00 0.00 0
Rising main (mtr.) 1 100.00 0.00 0
Sewer Line (km.) 1 5.60 0.00 0
STP (MLD) 1 220.00 41.10 37
16 Saharanpur Saharanpur I&D and STP works at Saharanpur NGP2-EAP HAM 16-Jun-2022 577.23 266.34 20.55 290.34 1 135.00 61 M/s Enviro Infra Engineers Ltd, Bhugan Infracon Pvt. Ltd. & Micro Transmission System, JV 343.88 01-Nov-2025 31-Oct-2027 +0.00
7.00
+0.00
10.27
Effluent Disposal Line (km.) 1 0.10 4.00 0 23-Feb-2026
  • In the review meeting on 25.04.25 at NMCG, UPJN-R/PE were asked to work out on the possible alternatives options like retaining wall option, backfilling option or others etc. Post which UPJN-R and PE had to work on optimization of the solution and comeback with all possible solution. Accordingly, additional cost implication worth Rs. 81 crore for STP due to level difference sent to NMCG on 21.04.25
  • Out of various feasible technical solutions to counter the implication arose due to mis-match of site data, option no. 4 has been approved in-principle by NMCG and communicated vide letter no. Pr-13011/1/2022 – O/o PS NMCG dated 03.10.2025. Concessionaire have to submit the detailed estimate with in one month.
  • Effective date of start 01.11.2025 given to concessionaire vide Lt. 1077/122(Namami Gange)132 dt. 31.10.2025
  • About 6.0 m level differnces as given in tender document and actual site level. as discussed NMCG meeting held on 07.01.2025.
  • LOA issue on dt. 26.07.2024. CA signed on dated 27.09.2024. Financial Closure documents submitted in NMCG, is under scrutiny.
01-Nov-2027 01-Nov-2027
Interception And Diversion 1 61.00 4.00 0
MPS (MLD) 1 172.30 4.00 0
Power Connection 1 1.00 4.00 0
Rising main (mtr.) 1 50.00 4.00 0
Sewer Line (km.) 1 16.00 4.00 0
STP (MLD) 1 135.00 8.00 0
17 Varanasi Varanasi I&D and Treatment works for Assi-BHU Area (Phase-II), Varanasi NGP DBOT 19-Oct-2022 308.09 97.62 7.81 172.94 1 55.00 2 M/s Enviro Infra Engineers limited MTS JV 151.55 07-Mar-2024 06-Dec-2025 +0.00
98.00
+0.00
86.20
Co-Treatment Facility(KLD) 1 10.00 0.00 0 24-Feb-2026
  • STP and IPS are commissioned
  • 55 MLD STP has been commissioned with the flow of 8 MLD STP Bhagwanpur
  • Finishing works are in progress
  • Power connection of MPS done. MPS shall be commissioned on 18.02.2026
  • STP under trial-run
No delay No delay 28-Feb-2026 06-May-2026
Effluent Disposal Line (km.) 1 1.32 0.00 17
IPS (MLD) 1 6.00 0.00 24
MPS (MLD) 1 50.00 0.00 23
Nala Tapping Arrangement ( No.) 1 2.00 0.00 8
Rising main (mtr.) 1 2.10 0.00 12
STP (MLD) 1 55.00 0.00 30
18 Unnao Unnao I&D of Drains and STP works in Unnao (15MLD) NGP HAM 28-Jul-2017 102.20 43.73 3.22 55.25 1 15.00 1 M/s KRMPL Kanpur 68.68 11-Oct-2019 10-Jul-2021
10-Jul-2021
15-Mar-2023
15-May-2025
15-Oct-2022
15-Sep-2021
25-Feb-2022
30-Apr-2023
30-Jun-2024
30-Jun-2025
30-May-2025
30-Nov-2025
30-Sep-2025
31-Dec-2024
31-Dec-2025
31-Jul-2024
31-Mar-2025
31-Mar-2026
31-Oct-2025
+0.00
99.00
+0.00
52.01
Boundary wall, staff quarter 1 1.00 92.00 74 24-Feb-2026
  • 1200 mm RCC Pipe 399.80meter work laying out of 399.80meter sewer line is done and pending construction of 02 Manhole (MH 31 & MH 44) at present, dewatering in Manhole No. 44 is in progress and 02 Manhole (MH 116 & MH 37) is joint repairing work pending. KRMPL deployed 6 manpower at site. Dewatering & Cleaning of 543meter work in progress (523meter done) balance 20meter work in progress KRMPL deployed cleaning of Sewer line 8 manpower. STP operating daily from 11.1.2025 through temporary line but CCT is not functional till date due to commissioning of CCT WORK IS PENDING from KRMPL also material short fall PAD HEATER & Pressure switch. In consideration of the cash flow concerns affecting the project progress, A proposal of advance of Rs. 6.50 Cr. (2.00 Cr. For Unnap STP & Rs. 4.5 Cr. For Shuklaganj STP) against extra work amounting to Rs. 9.50 Cr. was sent to NMCG against which a tripartite agreement has been signed date 04.07.2025 between NMCG, UPJN(R) and M/s KRMPL to provided Special Interest-Bearing Advance to firm for expediting the work and against it an amount of Rs. 3.18 Cr. has been paid as an advance to firm. I&D and STP works at Unnao is ongoing under Namami Gange, likely to be completed by March-26
The scheme is based on Hybrid Annuity Mode (HAM), 40% of the work cost was to be paid by NMCG, 40% by the lending bank (Bank Lender) and 20% was to be borne by the executing firm, but due to KRMPL not receiving loan from any bank for Hybrid Annuity Mode (HAM) works and the unavailability of necessary resources/labor and machinery by KRMPL, the progress of the work was affected, for which the firm was continuously directed to increase the availability of necessary resources i.e. labor and machinery at the work site and to complete the scheme within the stipulated time period, but the firm verbally cited its financial situation and did not increase any resources at the work site, due to which the work could not be completed within the stipulated time frame. Due to the delay in completing the work by the concessionaire firm M/s K.R.M.P.L., Kanpur, a financial penalty of Rs. 55.91 Lacs has also been imposed on the firm. Furthermore, a show cause notice has been issued to the executing firm by both the undersigned and higher authorities for unnecessary delay in completing the work. 30-Dec-2023 31-Mar-2026
Connecting Sewer 1100mm 1 3.20 95.00 33
Effluent Channel 1 300.00 96.00 48
Extra Item : Laying of 1200mm dia gravity sewer li 1 230.00 100.00 24
Interception & Diversion of City Jail Drain (Nala 1 1.00 98.00 45
MPS (15M dia 40MLD) 1 1.00 98.00 48
Online Monitoring System for STP (1 inlet+1 outlet 1 1.00 90.00 47
Rising Main (750mm dia) 1 100.00 98.00 47
STP (MLD) 1 15.00 98.00 47
19 Kanpur Nagar Interception & Diversion Of 14 Untapped Drains Of Kanpur City (Along with Supplementary Works) NGP2-NON EAP DBOT 02-May-2025 138.11 97.17 7.77 2.03 0 0.00 14 M/s Technocraft Ventures Limited 79.39 09-Jan-2026 08-Jul-2027 +0.00
0.00
+0.00
0.00
Construction of SPS and Lift Station (Nos) 1 7.00 0.00 0 23-Feb-2026
  • Conditional Assessment Survey, flow measurement of drains are being done by firm.
01-Jan-1900 08-Jul-2027
Interception and Diversion Work of Drains (Nos) 1 14.00 0.00 0
Laying of Diversion Sewer (meter) 1 2515.00 0.00 0
Laying of Rising main (meter) 1 11253.00 0.00 0
Miscellaneous Works 1 1.00 0.00 0
20 PrayagRaj Prayagraj Interception, Diversion of Balance 13 drains and Augmentation of Salori STP capacity by 43 MLD (Sewerage District-C) at Prayagraj Uttar Pradesh under DBOT mode NGP DBOT 14-Mar-2023 331.75 180.27 11.22 140.27 1 43.00 13 M/s HNB Private ltd. - M/s Tirupati Cements Products (JV) 204.40 19-Mar-2024 18-Aug-2025 +0.80
90.59
+0.00
81.92
Effluent Disposal Line (km.) 1 0.30 80.00 16 23-Feb-2026
  • Casting of 10th Lift of Wall at AB Culvert SPS has been completed.Compound wall & Sinking work is under progress
  • 2670 m laying of Rising main completed. Balance Laying is under progress.
  • Sitaram Ghat SPS- RCC work for wet well is under progress.
  • 1600 m laying of gravity intercepter line has been completed. Manhole construction work is under progress.
  • RCC work for I&D is under progress.
  • 43 MLD Salori STP partially commissioned on dated 31.12.2025.
  • RCC work for PTU, SBR Basin, CCT Unit, MCC Room ,Chlorination room, Air Blower, Sludge Dewatering Unit & TEPS is completed.
  • RCC work for chlorine tonner yard is under Progress.
  • Tiles, putti, painting and other finishing work for all unit of STP is under Progress.
  • RCC work completed for Admin Building and Staff quarter, Brick work & Plaster is under progress.
Progress was hampered due to site submergence in 2024, Construction of River front road, Mahakumbh-2025 and site submergence in 2025 during monsoon. 30-Apr-2026 30-Apr-2026
Effluent Pumping Station (MLD) 1 43.00 99.00 29
Interception And Diversion 1 13.00 54.00 8
IPS (MLD) 1 2.20 59.00 20
MPS (MLD) 1 32.00 65.00 16
Rehabilitation of Sewer Line 1 3.30 0.00 0
Rising main (mtr.) 1 4070.00 89.00 20
Sewer Line (km.) 1 2.16 82.00 8
STP (MLD) 1 43.00 96.00 106
21 PrayagRaj Prayagraj Interception, Diversion of Balance 7 drains and Augmentation of Rajapur STP capacity by 90 MLD (Sewerage District-D) at Prayagraj Uttar Pradesh under DBOT mode NGP DBOT 27-Jan-2023 475.98 242.85 15.24 217.89 1 90.00 7 M/s Triveni Engineering and Industries 309.74 24-Aug-2024 23-Feb-2026 +1.92
68.54
+0.00
62.40
Effluent Disposal Line (km.) 1 0.30 70.00 4 23-Feb-2026
  • Plinth Beam Casting is Completed for PTU, Earth Filling is under Progress.
  • RCC Casting of outer wall of SBR Basin 1&3 is completed, Partition wall is under progress.
  • RCC Casting of outer wall up to 3rd lift of SBR Basin 2&4 is completed, 4th Lift is under progress.
  • RCC work for CCT is completed.Weir wall is under progress.
  • TEPH 2nd lift of Wall is completed. Balance work is in progress.
  • RCC work of workshop Building is completed, Brick work is in progress.
  • Column upto plinth beam work of Air Blower Building is completed and Tie Beam work is under progress.
  • Admin Building, Sub Station ,Chlorination tonner room & MCC Room - Plinth Beam and column work is under Progress.
  • RCC casting up to 10th Lift of Rajapur SPS (56 MLD) is completed. Sinking is under progress.
  • RCC casting up to 6th Lift of Mumfordganj SPS (39 MLD) is completed. Sinking is under progress.
  • Shifting of Existing Rising main inside Mumfordganj SPS Campus work is completed.
  • 2850 m laying of Rising main completed. Balance Laying is under progress.
  • 850 m laying of Gravity main (Sadar Bazar) & 1391 m laying of Gravity main (Sankar Ghat) completed Balance Laying is under progress.
  • RCC work completed for 2 Nos I&D , work is under progress for 4 Nos. I&D.
  • Work was hampered due to Vehical restriction and overcrowding during Mahakumbh -2025, River Front road construction and Flood in 2024 &2025.
Work was hampered due to Vehical restriction and overcrowding during Mahakumbh -2025, River Front road construction and Flood in 2024 &2025. 23-Feb-2026 23-Feb-2026
Effluent Pumping Station (MLD) 1 90.00 45.00 4
Interception And Diversion 1 7.00 70.00 25
MPS (MLD) 2 95.00 51.00 60
Rehabilitation of Bund and Bund Road 1 1.00 18.00 0
Rising main (mtr.) 1 3450.00 85.00 4
Sewer Line (km.) 1 4.20 79.00 12
STP (MLD) 1 90.00 70.00 96
22 PrayagRaj Prayagraj Interception, Diversion of Balance discharge of 02 drains and 50 MLD STP to Augment existing Treatment Capacity (80 MLD) Naini STP for Sewerage District-A at Prayagraj Uttar Pradesh under DBOT mode NGP DBOT 05-Sep-2023 186.47 83.71 5.44 97.32 1 50.00 2 M/s JWIL-SSG (Joint Venture) 95.57 04-Mar-2025 03-Jul-2026 +4.36
44.94
+0.00
8.48
Co-treatment Unit for Fecal Sludge (KLD) 1 20.00 0.00 0 23-Feb-2026
  • Structure design & drawing of SBR, Claritube settler, Staff quarter, CCT, PTU, Admin Building cum Blower Room and Workshop Building has been approved.
  • Excavation, PCC of work shop building is completed reinforcement work for raft is under progress.
  • BEP of 50 MLD STP has been approved.
  • Excavation, Reinforcement and Concreting work upto slab level is completed in PTU.
  • Piling work of I&D Structure is under progress.
  • Reinforcement work of 11th lift of SPS is under progress.
  • Casting of columns of claritubesettler is completed and shuttering work of beam and grade slab is under progress.
  • Staff quarter upto ground floor column is completed and Shuttering and reinforcement work for Ground Floor beam and slab is completed.
  • Gravel padding, PCC and raft of Admin Building is completed and reinforcement & shuttering work of plinth beam is under progress.
  • Finishing work of Security Cabin is under progress.
  • BEP and Structure design and drawing has been Approved for 2.90 MLD Bargad Ghat SPS.
  • Survey, Design and Drawing work of remaining structure is in progress.
  • oncreting work of Grid Slab of SBR basin-1, 2 & 3 is completed and shuttering, reinforcement and concreting work of basin wall - 1& 2 upto 80% height is completed. Reinforcement and concreting work of SBR basin - 4 is under progress. PCC work of SBR basin -4 is completed and reinforcement work is under progress.
  • Soil testing of STP & SPS site has been completed.
  • Gravel padding, PCC and Reinforcement of CCT raft is completed and concreting work of wall is under progress.
  • Workshop Building Footing work is completed column work is in progress.
  • Dewatering Building foundation work in under progress.
Site submergence during flood period. Firm has requested for technology change and the same was rejected by NMCG, New Delhi on dated 27.05.2025 Notice regarding LD has been issued to the firm for delay 03-Jul-2026 03-Jul-2026
Interception And Diversion 1 2.00 76.00 24
IPS (MLD) 1 2.90 45.00 46
Rising main (mtr.) 1 100.00 0.00 0
Sewer Line (km.) 1 0.06 1.00 0
STP (MLD) 1 50.00 45.00 140
23 Mathura Mathura Mathura sewerage scheme (I&D and STP Works for balance drain) NGP2-NON EAP HAM 07-Sep-2022 292.56 149.85 9.61 133.10 1 60.00 4 M/s EIEL Mathura Infra Engineers Private Limited 240.01 30-Nov-2024 29-Nov-2026 +7.58
74.57
+0.00
117.52
I/C Sewer line (Mtr.) 1 1970.00 90.38 4 24-Feb-2026
  • LOA issued to L1 Bidder on on 27.09.2023. CA signed on 12.12.2023. Effective date of start shall be to concessionaire after financial closure.
  • Effective date of start has been given to concessionaire as 30.11.2024.
  • IPS Kala Patthar civil work and its Rising main has been completed
  • SBR basin and MPS construction work is in progress in STP premises.
  • Dairy farm IPS rising main laying work is in progress.
No Delay - 30-Nov-2026 30-Nov-2026
Interception And Diversion 1 4.00 57.70 4
IPS (MLD) 2 47.00 66.60 13
MPS (MLD) 1 60.00 96.00 8
Rising main (mtr.) 1 9290.00 95.28 8
STP (MLD) 1 60.00 71.00 10
24 Lucknow Pollution Abatement Of Gomti River (Phase 1 Part 1) Lucknow NGP DBOT 29-Jul-2024 240.93 123.45 6.97 110.51 2 42.50 2 M/s R.K. Engineers- Khilari Infrastructure (JV) 187.90 07-Sep-2024 06-Jun-2026 +0.06
88.00
+0.00
117.65
Interception And Diversion 1 1.00 3.00 0 23-Feb-2026
  • 39 MLD STP Daulatganj Operation & Maintenance started on dt. 05.11.2024.
  • Date of start of 3.5 MLD Barikala STP is given on dt. 07.09.2024 to M/s R.K. Engineers Sales Ltd. - Khilari Infrastructures (JV). SBR Basin -Hydro testing work is in progress. CCT - Hydro testing work is in progress. MPS -Inlet Channel raft reinforcement work is in progress. PTU - Slab reinforcement and shuttering work is in progress. HT Building- Roof slab casting completed. Cable trench work is in progress. Admin Building -Plinth beam reinforcement, shuttering & casting work is in progress. SHU- Sludge sump wall 1st lift casting completed. Transformer yard - Base slab reinforcement work is in progress. DG- Pletform wall reinforcement, shuttering & casting work is in progress. Supply of Deacanter & Defuser completed.
Slow progress by firm. L.D. imposed Rs. 66,74,000.00 on firm 06-Jun-2026 06-Jul-2026
MPS 1 3.50 29.05 0
STP (MLD) 2 42.50 81.94 51
Uppgradation of SPS 3 3.00 100.00 0
25 Lucknow Lucknow Pollution Abatement of Gomti River (Phase-II, Part-I) Lucknow NGP DBOT 30-Jan-2023 264.67 137.55 8.53 118.60 1 50.00 3 M/s R.K. Engineers- Khilari Infrastructure (JV) 187.74 14-Jun-2024 13-Mar-2026 +0.36
5.71
+0.00
7.22
Interception And Diversion 1 3.00 4.68 0 23-Feb-2026
  • Staff quarter work is completed. BEP is approved. Design & Drawing work is in progress. SBR Basin-4 raft reinforcement work is in progress.. SBR Basin-3 Leveling & dressing work is in progress. SBR Basin-2 excavation work is in progress. IPS - Excavation and shoring work is in progress. Faizullaganj (U/S) I&D - Approach drain excavation, PCC, reinforcement, shuttering and casting work is in progress. Rising main - Pipe laying work is in progress.
Slow progress by firm. L.D. imposed Rs. 64,13,000.00 on firm 13-Apr-2026 13-Apr-2026
Rising main (mtr.) 1 3500.00 12.89 0
SPS (MLD) 1 22.60 1.83 0
STP (MLD) 1 50.00 5.65 33