| 1 |
Unnao |
Shuklaganj |
I&D of Drains and STP works in Shuklaganj (05MLD) |
Ganga Vishnu Drain |
Untapped Drains |
I&D and STP works at Shuklaganj is ongoing under Namami Gange, likely to be completed by March-26 |
05-Jan-2026 10:33 AM |
| 2 |
Unnao |
Shuklaganj |
I&D of Drains and STP works in Shuklaganj (05MLD) |
Indira Nagar Drain |
Untapped Drains |
The tapping of domestic sewage through I&D was completed on 30.12.2025, and the project trial run has commenced. The trial run will continue for three months, after which the STP will operate at full capacity |
05-Jan-2026 10:33 AM |
| 3 |
Unnao |
Shuklaganj |
I&D of Drains and STP works in Shuklaganj (05MLD) |
Manohar Nagar Nala Ist (New) |
Untapped Drains |
The tapping of domestic sewage through I&D was completed on 30.12.2025, and the project trial run has commenced. The trial run will continue for three months, after which the STP will operate at full capacity |
05-Jan-2026 10:33 AM |
| 4 |
Unnao |
Shuklaganj |
I&D of Drains and STP works in Shuklaganj (05MLD) |
Railway Bridge Drain |
Untapped Drains |
The tapping of domestic sewage through I&D was completed on 30.12.2025, and the project trial run has commenced. The trial run will continue for three months, after which the STP will operate at full capacity |
05-Jan-2026 10:34 AM |
| 5 |
Unnao |
Shuklaganj |
I&D of Drains and STP works in Shuklaganj (05MLD) |
Manohar Nagar Nala IInd (New) |
Untapped Drains |
The tapping of domestic sewage through I&D was completed on 30.12.2025, and the project trial run has commenced. The trial run will continue for three months, after which the STP will operate at full capacity |
05-Jan-2026 10:34 AM |