| S.No | Work Component | Capacity/Length/No | Technology | Physical Progress(%) | Last Update Date |
|---|---|---|---|---|---|
| 1 | STP (MLD) | 17.00 | NA | 0.50 | 28-Jul-2026 02:20 PM |
| 2 | STP (MLD) | 5.00 | NA | 0.50 | 28-Jul-2026 02:20 PM |
| 3 | STP (MLD) | 3.00 | NA | 0.50 | 28-Jul-2026 02:20 PM |
| S.No | Work Component | Capacity/Length/No | Technology | Physical Progress(%) | Last Update Date |
|---|---|---|---|---|---|
| 1 | STP (MLD) | 17.00 | NA | 0.50 | 28-Jul-2026 02:20 PM |
| 2 | STP (MLD) | 5.00 | NA | 0.50 | 28-Jul-2026 02:20 PM |
| 3 | STP (MLD) | 3.00 | NA | 0.50 | 28-Jul-2026 02:20 PM |