Project Completion Certificate (Ground Water)
Scheme ID: 20007059 Name of Scheme: Bahloulpur No. of Villages: 3 No. of Habitation Covered: 10
Total Population Covered: 4681 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 22-Mar-2023 Actual Date of Completion (Capex): 26-Nov-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 30.5 / 49.87 Bahloulpur Neewa 26.4471563 82.87033312
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PN-6 63 7.638
2 HDPE PN-6 75 3.321
3 HDPE PN-6 90 1.366
4 HDPE PN-6 110 1.547
5 HDPE PN-6 140 1.91
6 HDPE PN-6 200 0.699
HSC Connection
Sno. Total Nos.
Other Details
3.03
3.45
3.43
10-Jul-2025
24-Nov-2025