Project Completion Certificate (Ground Water)
Scheme ID: 20007172 Name of Scheme: Naserpur Tulsepur - 168243 No. of Villages: 3 No. of Habitation Covered: 9
Total Population Covered: 5058 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 22-May-2026 Actual Date of Completion (Capex): 12-Jul-2026
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 24/65 Naserpur Tulsepur 26.48203723 82.62577597
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 VT Pump -1 1200 LPM Naserpur Tulsepur 26.48203723 82.62577597
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 350 KL / 14 mtr Naserpur Tulsepur 26.48203723 82.62577597
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI K-9 200 18
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PN-6 63 9.74
2 HDPE PN-6 75 2.01
3 HDPE PN-6 90 2.77
4 HDPE PN-6 110 1.512
5 HDPE PN-6 140 1.69
6 HDPE PN-6 200 0.657
HSC Connection
Sno. Total Nos.
1 568
Other Details
363.73
397.80
330.24
20-Feb-2026
12-Jul-2026