| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20011676 | Name of Scheme: Shahkarampur Giladi Village Water Supply Scheme | No. of Villages: 1 | No. of Habitation Covered: 3 |
| Total Population Covered: 2356 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 09-Feb-2024 | Actual Date of Completion (Capex): 10-Aug-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewells | 12.02 MTR/138.03 MTR | Shahkarampur Giladi | 29.358461 | 78.353077 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | SUBMERSIBLE PUMP 12.50 HP | 525 LMP/44 MTR | Shahkarampur Giladi | 29.358607 | 78.35094 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 150KL /16 MTR | Shahkarampur Giladi | 29.358607 | 78.35094 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | K-7 DI PIPE | 100 | 0.022 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE PIPE PN 6: CLASS PE- 100 | 110 | 0.077 | |
| 2 | HDPE PIPE PN 6: CLASS PE- 100 | 90 | 0.080 | |
| 3 | HDPE PIPE PN 6: CLASS PE- 100 | 75 | 0.826 | |
| 4 | HDPE PIPE PN 6: CLASS PE- 100 | 63 | 4.885 | |
| 5 | HDPE PIPE PN 6: CLASS PE- 100 | 140 | 0.300 | |
| 6 | HDPE PIPE PN 6: CLASS PE- 100 | 160 | 0.300 | |
| 7 | HDPE PIPE PN 6: CLASS PE- 100 | 180 | 2.922 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 380 |