Project Completion Certificate (Ground Water)
Scheme ID: 20012312 Name of Scheme: Victoriya Ganj No. of Villages: 1 No. of Habitation Covered: 14
Total Population Covered: 8800 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 14-Jun-2023 Actual Date of Completion (Capex): 12-Sep-2023
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 27.07 M/ 88.77 M Victoriya Ganj 27.270282 80.297185
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 0.800 M³ per Min /45Mtr Victoriya Ganj 27.270282 80.297185
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 250 KL/ 18 Mtr Victoriya Ganj 27.269415 80.296776
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 D. I. Pipe 150 0.0093
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6, Class PE-100 63 10.4326
2 HDPE Pipe PN-6, Class PE-100 75 7.7386
3 HDPE Pipe PN-6, Class PE-100 90 3.7444
4 HDPE Pipe PN-6, Class PE-100 110 3.0209
5 HDPE Pipe PN-6, Class PE-100 125 0.041
6 HDPE Pipe PN-6, Class PE-100 140 2.312
7 HDPE Pipe PN-6, Class PE-100 180 1.3715
8 HDPE Pipe PN-6, Class PE-100 200 2.9531
HSC Connection
Sno. Total Nos.
1 1188
Other Details
4.35
0.00
4.26
11-Dec-2023
24-Dec-2024