| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20012886 | Name of Scheme: Turkimau | No. of Villages: 2 | No. of Habitation Covered: 3 |
| Total Population Covered: 3200 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 05-Feb-2022 | Actual Date of Completion (Capex): 31-Dec-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tube well | 24/156.80 | Turkimau | 26.261203 | 79.997384 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible | 49.30/66 | Turkimau | 26.261203 | 79.997384 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 200/16 | Turkimau | 26.261203 | 79.997384 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 150 | 0.020 | As per Site |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 6.0 | As per Site |
| 2 | HDPE | 75 | 0.93 | As per Site |
| 3 | HDPE | 90 | 0.15 | As per Site |
| 4 | HDPE | 110 | 1.89 | As per Site |
| 5 | HDPE | 140 | 0.39 | As per Site |
| 6 | HDPE | 160 | 0.25 | As per Site |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 535 |