| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20015016 | Name of Scheme: Sarai Jalal | No. of Villages: 1 | No. of Habitation Covered: 2 |
| Total Population Covered: 2440 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 12-Oct-2022 | Actual Date of Completion (Capex): 02-Aug-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tube well | 24.07 Mtr 149.23 Mtr | Sarai Jalal | 26.70125* | 79.137743* |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible | 30.01 (M3/Hr.)/ 49 Mtr. | Sarai Jalal | 26.70125* | 79.137743* |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 80 | 0.0150 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 5.466 | |
| 2 | HDPE | 110 | 1.144 | |
| 3 | HDPE | 160 | 0.314 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 367 |