| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20015525 | Name of Scheme: Chavar Khas WSS | No. of Villages: 3 | No. of Habitation Covered: 3 |
| Total Population Covered: 2410 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 31-Dec-2024 | Actual Date of Completion (Capex): 25-Dec-2023 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBEWELL | 18.08/79.38 | CHAVAR KHAS | 27.956074 | 79.649088 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | VT PUMP-1 | 32.4M3/45M | CHAVAR KHAS | 27.956074 | 79.649088 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT-1 | 150KL-16M | CHAVAR KHAS | 27.956003 | 79.649015 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI -K7 | 125 | 0.028 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE/6KG | 63 | 6.709 | |
| 2 | HDPE/6KG | 75 | 0.845 | |
| 3 | HDPE/6KG | 90 | 2.675 | |
| 4 | HDPE/6KG | 110 | 0.280 | |
| 5 | HDPE/6KG | 140 | 0.101 | |
| 6 | HDPE/6KG | 160 | 0.940 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 351 |