Project Completion Certificate (Ground Water)
Scheme ID: 20018508 Name of Scheme: Dehjuri No. of Villages: 3 No. of Habitation Covered: 14
Total Population Covered: 2642 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 22-May-2023 Actual Date of Completion (Capex): 21-Mar-2026
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tube well -300X150 30.13/196.22 Dehjuri 25.741598 82.526305
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Pump-12.5HP 600/49.90 Dehjuri 25.741598 82.526305
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 175KL-14M Dehjuri 25.74152 82.526255
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI K-9 150 0.03
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE PN-6 160 0.051
2 HDPE PIPE PN-6 140 0.264
3 HDPE PIPE PN-6 110 1.661
4 HDPE PIPE PN-6 90 0.961
5 HDPE PIPE PN-6 75 0.319
6 HDPE PIPE PN-6 63 9.458
HSC Connection
Sno. Total Nos.
1 396
Other Details
2.48
2.32
2.22
21-Mar-2026
22-Mar-2026