| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20019270 | Name of Scheme: Aldi Village Water Supply Scheme | No. of Villages: 1 | No. of Habitation Covered: 1 |
| Total Population Covered: 5049 | Base Year: 2022 | Intermediate Year: 2035 | Design Year: 2052 |
| Date of Completion (As per Contract): 27-Dec-2023 | Actual Date of Completion (Capex): 19-Jul-2025 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 30/50 | Aldi | 29.4484764 | 77.38191532 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersibile | 1050/69 | Aldi | 29.4484764 | 77.38191532 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 325KL/12m | Aldi | 29.4484764 | 77.38191532 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 150 | 0.021 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 4.801 | |
| 2 | HDPE | 75 | 0.630 | |
| 3 | HDPE | 90 | 0.387 | |
| 4 | HDPE | 110 | 1.120 | |
| 5 | HDPE | 160 | 0.546 | |
| 6 | HDPE | 200 | 0.410 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 1094 |