Project Completion Certificate (Ground Water)
Scheme ID: 20019814 Name of Scheme: Kataiya No. of Villages: 2 No. of Habitation Covered: 2
Total Population Covered: 2900 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 31-Dec-2024 Actual Date of Completion (Capex): 03-May-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 22.00/93.57 KATAIYA 28.076052 79.670671
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 VT PUMP - 1 38.52 M3 / 45 M KATAIYA 28.076052 79.670671
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT - 1 200 KL - 18 M KATAIYA 28.076057 79.670676
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI - K7 125 0.030
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE / 6 KG 63 2.452
2 HDPE / 6 KG 75 0.327
3 HDPE / 6 KG 90 0.124
4 HDPE / 6 KG 110 1.692
5 HDPE / 6 KG 140 1.137
6 HDPE / 6 KG 160 0.050
7 HDPE / 6 KG 180 0.548
HSC Connection
Sno. Total Nos.
1 535
Other Details
2.04
0.00
2.04
06-Aug-2024
06-Dec-2024