Project Completion Certificate (Ground Water)
Scheme ID: 20019916 Name of Scheme: Bangaon No. of Villages: 1 No. of Habitation Covered: 5
Total Population Covered: 4770 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 03-Aug-2023 Actual Date of Completion (Capex): 30-Aug-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tube well 21/59.78 BANGAON 26º 25' 49.355" N 82º 17' 51.761" E
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 VTPump 39/44 BANGAON 26º 25' 49.355" N 82º 17' 51.761" E
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 RCC-Zink Alum Tank 175/12 BANGAON 26º 25' 49.355" N 82º 17' 51.761" E
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI Pipe K-7 100 0.035
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6: Class PE-100 63 12.818
2 HDPE Pipe PN-6: Class PE-100 75 4.416
3 HDPE Pipe PN-6: Class PE-100 90 1.788
4 HDPE Pipe PN-6: Class PE-100 110 0.439
5 HDPE Pipe PN-6: Class PE-100 140 0.371
6 HDPE Pipe PN-6: Class PE-100 160 0.148
7 HDPE Pipe PN-6: Class PE-100 200 0.025
HSC Connection
Sno. Total Nos.
1 582
Other Details
2.52
0.00
0.00
27-Dec-2026
28-Dec-2025