Project Completion Certificate (Ground Water)
Scheme ID: 20020474 Name of Scheme: BELWA KHURD, SONBARSA KHURD, VISHUNPUR KHURD No. of Villages: 3 No. of Habitation Covered: 8
Total Population Covered: 7220 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 04-Feb-2024 Actual Date of Completion (Capex): 15-Jun-2026
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 30/11.73 Belwa Khurd, Sonbarsa Khurd, Vishunpur Khurd 26.739 83.566
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible Pump 90/44 Belwa Khurd, Sonbarsa Khurd, Vishunpur Khurd 26.739 83.566
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 Overhead Tank-1 450/16 Belwa Khurd, Sonbarsa Khurd, Vishunpur Khurd 26.739 83.566
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 200 0.035 Laying Completed
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 17.73 Laying Completed
2 HDPE 75 1.29 Laying Completed
3 HDPE 90 1.46 Laying Completed
4 HDPE 110 1.53 Laying Completed
5 HDPE 140 1.64 Laying Completed
6 HDPE 160 2.29 Laying Completed
7 HDPE 200 0.14 Laying Completed
HSC Connection
Sno. Total Nos.
1 1247
Other Details
4.06
0.00
4.57
06-Feb-2025
15-Jun-2026