Project Completion Certificate (Ground Water)
Scheme ID: 20020911 Name of Scheme: Husainpur No. of Villages: 3 No. of Habitation Covered: 10
Total Population Covered: 4140 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 22-May-2023 Actual Date of Completion (Capex): 18-Oct-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tube well -300X200 31.07/119.10 Husainpur 25.571466 82.679347
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Pump-20HP 900/49.50 Husainpur 25.571466 82.679347
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 250KL/14M Husainpur 25.571451 82.679352
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI K-9 200 0.02
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE PN-6 200 0.071
2 HDPE PIPE PN-6 140 0.731
3 HDPE PIPE PN-6 110 1.250
4 HDPE PIPE PN-6 90 0.621
5 HDPE PIPE PN-6 75 2.050
6 HDPE PIPE PN-6 63 14.728
HSC Connection
Sno. Total Nos.
1 573
Other Details
3.00
2.82
2.45
18-Oct-2025
19-Oct-2025