Project Completion Certificate (Ground Water)
Scheme ID: 20020943 Name of Scheme: TARBIYATPUR No. of Villages: 3 No. of Habitation Covered: 3
Total Population Covered: 4133 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 31-Dec-2024 Actual Date of Completion (Capex): 14-Mar-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 24.21 Mtr / 106.28 Mtr TARBIYATPUR 28.943549 78.059332
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 700 LPM / 54 Mtr TARBIYATPUR 28.943549 78.059332
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 200 Kl / 16 M TARBIYATPUR 28.943549 78.059332
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 150 0.029
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 7.956
2 HDPE 90 2.262
3 HDPE 110 0.654
4 HDPE 125 1.034
5 HDPE 140 0.470
6 HDPE 180 1.358
HSC Connection
Sno. Total Nos.
1 544
Other Details
3.28
3.28
2.71
31-Jul-2025
01-Aug-2025