Project Completion Certificate (Ground Water)
Scheme ID: 20021742 Name of Scheme: PAHALMAPUR GP WATER SUPPLY SCHEME No. of Villages: 3 No. of Habitation Covered: 3
Total Population Covered: 2561 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 01-Aug-2025 Actual Date of Completion (Capex): 28-Oct-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TW 50/150 Pahalmapur 25 81
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible pump 11/50 Pahalmapur 25 81
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 50/12 Pahalmapur 25 81
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI K9 80 0.03
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 140 0.072
2 HDPE 110 0.522
3 HDPE 75 1.509
4 HDPE 63 5.442
HSC Connection
Sno. Total Nos.
1 356
Other Details
2.22
0.00
0.00
21-Oct-2025
29-Oct-2025