Project Completion Certificate (Ground Water)
Scheme ID: 20021997 Name of Scheme: Karwa Bujurg pws No. of Villages: 1 No. of Habitation Covered: 4
Total Population Covered: 4250 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 22-Sep-2023 Actual Date of Completion (Capex): 10-Feb-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 33.00 Mtr/133.18 Mtr KARWA BUJURG 26.653013* 79.148372*
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE 54 M^3/45 Mtr KARWA BUJURG 26.653013* 79.148372*
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 250 KL/12Mtr KARWA BUJURG 26.653013* 79.148372*
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 150 0.017
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 4.891
2 HDPE 75 0.482
3 HDPE 90 1.819
4 HDPE 110 .470
5 HDPE 140 2.396
6 HDPE 180 .274
HSC Connection
Sno. Total Nos.
1 648
Other Details
2.20
2.67
2.67
13-May-2024
14-May-2024