| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20023905 | Name of Scheme: Bhabhi Wss | No. of Villages: 1 | No. of Habitation Covered: 1 |
| Total Population Covered: 2260 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 31-Dec-2024 | Actual Date of Completion (Capex): 31-Jul-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBEWELL | 21.12/96.6 | BHABHI | 27.279986 | 80.003248 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | VP PUMP -1 | 28.80/43 | BHABHI | 27.279986 | 80.003248 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT -1 | 150/12 | BHABHI | 27.279973 | 80.003364 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | K-7 | 125 | 0.030 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE/6KG | 63 | 11.328 | |
| 2 | HDPE/6KG | 75 | 1.535 | |
| 3 | HDPE/6KG | 110 | 1.797 | |
| 4 | HDPE/6KG | 140 | 0.023 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 362 |