Project Completion Certificate (Ground Water)
Scheme ID: 20024040 Name of Scheme: Abdul Kaliqpur Balram Gram Panchayat Water Supply No. of Villages: 2 No. of Habitation Covered: 2
Total Population Covered: 1776 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 06-Jul-2023 Actual Date of Completion (Capex): 20-Sep-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBE WELL 18/139.4 SHEKHPUR PUTTA 29.353838 78.40539
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE PUMP 400/47 SHEKHPUR PUTTA 29.353838 78.40539
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 125/12 SHEKHPUR PUTTA 29.353838 78.40539
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI-K7 100 0.021
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 5.565
2 HDPE 75 0.111
3 HDPE 90 1.028
4 HDPE 110 0.314
5 HDPE 140 0.107
HSC Connection
Sno. Total Nos.
1 329
Other Details
1.67
0.00
1.69
20-Mar-2026
21-Mar-2026