Project Completion Certificate (Ground Water)
Scheme ID: 20024481 Name of Scheme: MANIKPUR BISU PWS No. of Villages: 1 No. of Habitation Covered: 2
Total Population Covered: 5600 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 22-Sep-2023 Actual Date of Completion (Capex): 26-Jun-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tube Well 36.11/154.64 Manikpur Bisu 26.75473 79.046662
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 70(M³/Hr.)/56Mtr. Manikpur Bisu 26.75473 79.046662
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 350/16 Manikpur Bisu 26.75473 79.046662
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 D.I 150 0.069
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 5.153
2 HDPE 75 1.784
3 HDPE 90 1.758
4 HDPE 110 0.620
5 HDPE 140 1.116
6 HDPE 160 0.502
7 HDPE 180 0.544
HSC Connection
Sno. Total Nos.
1 987
Other Details
2.48
3.12
3.12
26-Jun-2024
27-Jun-2024