Project Completion Certificate (Ground Water)
Scheme ID: 20024836 Name of Scheme: Adhinpur Water Supply Scheme No. of Villages: 1 No. of Habitation Covered: 8
Total Population Covered: 4796 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 17-Sep-2022 Actual Date of Completion (Capex): 25-Apr-2026
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 27.12 / 80.51 Adhinpur 27.18528 82.26779
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 VT Pump-1 970 Adhinpur 27.18528 82.26779
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 275KL/14 Mtr Adhinpur 27.18528 82.26779
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 150 35.85
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 200 0.154
2 HDPE 140 1.621
3 HDPE 110 1.208
4 HDPE 90 0.682
5 HDPE 75 0.982
6 HDPE 63 5.759
HSC Connection
Sno. Total Nos.
1 490
Other Details
2.30
0.00
2.60
25-Jul-2026
25-Jul-2026