| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20025448 | Name of Scheme: NauGawan PWS | No. of Villages: 1 | No. of Habitation Covered: 4 |
| Total Population Covered: 3939 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 01-Jul-2021 | Actual Date of Completion (Capex): 02-Feb-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tube well | 32 M/ 140.30M | NAUGAWAN | 26.612102 | 79.624936 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible | 800 LPM/ 53M | NAUGAWAN | 26.6121.02 | 79.624936 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 250 KL/ 16M | NAUGAWAN | 26.6121.02 | 79.624936 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | D.I. | 150 | 8.80 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 5721 | |
| 2 | HDPE | 90 | 4356 | |
| 3 | HDPE | 110 | 344 | |
| 4 | HDPE | 125 | 1935 | |
| 5 | HDPE | 140 | 491 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 821 |