| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20025593 | Name of Scheme: Mirzapur Gram Panchayat Water Supply | No. of Villages: 1 | No. of Habitation Covered: 1 |
| Total Population Covered: 3276 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 06-Jul-2023 | Actual Date of Completion (Capex): 05-Feb-2025 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBEWELL | 24.05 / 120.71 | MIRZAPUR | 29.280059 | 78.503588 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | SUBMERSIBLE PUMP | 650 / 52 | MIRZAPUR | 29.280059 | 78.503588 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 200 KL / 12 MTR | MIRZAPUR | 29.280059 | 78.503588 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 100 | 0.040 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE PIPE | 63 | 3.5737 | |
| 2 | HDPE PIPE | 75 | 0.6666 | |
| 3 | HDPE PIPE | 90 | 0.0107 | |
| 4 | HDPE PIPE | 110 | 0.2269 | |
| 5 | HDPE PIPE | 125 | 0.0385 | |
| 6 | HDPE PIPE | 160 | 0.1293 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 510 |