Project Completion Certificate (Ground Water)
Scheme ID: 20026430 Name of Scheme: Shivpuri Timaruwa PWS No. of Villages: 3 No. of Habitation Covered: 7
Total Population Covered: 5460 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 22-Sep-2023 Actual Date of Completion (Capex): 15-Mar-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 27.08/170.22 MTR SHIVPURI TIMRAUWA 29.947201 79.072825
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBERMERSIBLE 72(M3/HR.)/56 MTR SHIVPURI TIMRAUWA 29.947201 79.072825
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 350 KL / 18 MTR SHIVPURI TIMRAUWA 29.947201 79.072825
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 D.I 200 0.030
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 4.716
2 HDPE 75 2.452
3 HDPE 90 1.346
4 HDPE 110 3.417
5 HDPE 140 0.978
6 HDPE 180 3.027
HSC Connection
Sno. Total Nos.
Other Details
3.02
4.43
4.43
15-Mar-2024
16-Mar-2024