Project Completion Certificate (Ground Water)
Scheme ID: 20035279 Name of Scheme: NONHAR WSS No. of Villages: 1 No. of Habitation Covered: 7
Total Population Covered: 4380 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 21-Oct-2023 Actual Date of Completion (Capex): 30-Aug-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tube well 18/86.80 NONHAR 26º 11' 15.418" N 82º 49' 21.267" E
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 VTPump 36/43 NONHAR 26º 11' 15.418" N 82º 49' 21.267" E
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 RCC- Zink Alum Tank 150/12 NONHAR 26º 11' 15.418" N 82º 49' 21.267" E
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI Pipe K-7 100 0.035
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6: Class PE-100 63 4.839
2 HDPE Pipe PN-6: Class PE-100 75 2.667
3 HDPE Pipe PN-6: Class PE-100 90 1.506
4 HDPE Pipe PN-6: Class PE-100 110 0.405
5 HDPE Pipe PN-6: Class PE-100 140 0.338
6 HDPE Pipe PN-6: Class PE-100 160 0.385
HSC Connection
Sno. Total Nos.
1 280
Other Details
1.86
0.00
1.83
22-Dec-2025
23-Dec-2025