Project Completion Certificate (Ground Water)
Scheme ID: 20036403 Name of Scheme: Navalpur Multi GP Water Supply Scheme No. of Villages: 5 No. of Habitation Covered: 5
Total Population Covered: 4460 Base Year: 2022 Intermediate Year: 2037 Design Year: 2022
Date of Completion (As per Contract): 30-Jul-2025 Actual Date of Completion (Capex): 30-Jul-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 100/102.01 Navalpur 82.338166 25.501495
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible Pump 52.78 Navalpur 82.338166 25.501495
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 ZnAl 250/14 Navalpur 82.338166 25.501495
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 200 0.030
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 8.870
2 HDPE 75 1.422
3 HDPE 90 1.390
4 HDPE 110 0.392
5 HDPE 140 1.432
6 HDPE 160 0.288
7 HDPE 200 1.017
HSC Connection
Sno. Total Nos.
1 749
Other Details
3.30
3.52
3.52
31-Oct-2025
01-Nov-2025