Project Completion Certificate (Ground Water)
Scheme ID: 20044209 Name of Scheme: Karchalpur No. of Villages: 2 No. of Habitation Covered: 3
Total Population Covered: 3330 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 13-Mar-2024 Actual Date of Completion (Capex): 10-Mar-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tube well 16.03/125.85 Karchalpur 26.16382 80.513411
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submerssible Pump 700/55 Karchalpur 26.16382 80.513411
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 200/16 Karchalpur 26.163879 80.513151
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI PIPE K-7 150 0.035
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE 63 9.431
2 HDPE PIPE 75 0.963
3 HDPE PIPE 90 2.231
4 HDPE PIPE 110 3.821
5 HDPE PIPE 140 1.710
6 HDPE PIPE 160 0.904
HSC Connection
Sno. Total Nos.
1 700
Other Details
3.38
0.00
3.38
05-Aug-2025
06-Aug-2025