Project Completion Certificate (Ground Water)
Scheme ID: 20050687 Name of Scheme: RAM NAGAR WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 8
Total Population Covered: 3150 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 17-Dec-2022 Actual Date of Completion (Capex): 29-Oct-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 300X300 18.03 / 64.07 RAMNAGAR 25.750290 82.379722
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 12.5 HP 655 LPM/43M RAMNAGAR 25.750290 82.379722
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 200 KL /12 M RAMNAGAR 25.750227 82.379657
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI,K-7 125 0.035 YES
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 90 1.696 YES
2 HDPE 75 1.975 YES
3 HDPE 63 13.713 YES
4 HDPE 100 0.07 YES
5 HDPE 140 0.402 YES
6 HDPE 160 0.055 YES
7 HDPE 180 0.076 YES
HSC Connection
Sno. Total Nos.
1 430
Other Details
2.61
2.61
2.00
29-Oct-2025
15-Jun-2025