Project Completion Certificate (Ground Water)
Scheme ID: 20051728 Name of Scheme: LAKHIPUR WATER SUPPLY SCHEME No. of Villages: 3 No. of Habitation Covered: 4
Total Population Covered: 3190 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 02-Dec-2023 Actual Date of Completion (Capex): 10-Apr-2026
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 24.00/83.30 LAKHIPUR 26.231473 82.050303
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 VT Pump-1 670LPM/44M LAKHIPUR 26.231473 82.050303
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 200KL/14M LAKHIPUR 26.231473 82.050303
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI Pipe K-7 150 0.024
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE-PN-6 , PE-100 63 13.909
2 HDPE-PN-6 , PE-100 75 3.731
3 HDPE-PN-6 , PE-100 90 1.304
4 HDPE-PN-6 , PE-100 110 1.611
5 HDPE-PN-6 , PE-100 140 0.234
6 HDPE-PN-6 , PE-100 160 0.031
7 HDPE-PN-6 , PE-100 200 0.076
HSC Connection
Sno. Total Nos.
1 650
Other Details
2.62
0.00
2.73
15-Nov-2026
01-May-2026