Project Completion Certificate (Ground Water)
Scheme ID: 20056507 Name of Scheme: NIMTINI WSS No. of Villages: 1 No. of Habitation Covered: 12
Total Population Covered: 6160 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 26-Dec-2023 Actual Date of Completion (Capex): 11-Jul-2026
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tube well 33.01 /45.29 NIMTINI 26° 21' 37.44" N 82° 49' 11.568" E
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 VTPump 63/44 NIMTINI 26° 21' 37.44" N 82° 49' 11.568" E
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 RCC-Zink Alum Tank 300/14 NIMTINI 26° 21' 37.44" N 82° 49' 11.568" E
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI Pipe K-7 150 0.035
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6: Class PE-100 63 14.909
2 HDPE Pipe PN-6: Class PE-100 75 7.078
3 HDPE Pipe PN-6: Class PE-100 90 1.038
4 HDPE Pipe PN-6: Class PE-100 110 0.604
5 HDPE Pipe PN-6: Class PE-100 140 0.833
6 HDPE Pipe PN-6: Class PE-100 160 0.511
7 HDPE Pipe PN-6: Class PE-100 200 0.821
HSC Connection
Sno. Total Nos.
1 774
Other Details
396.74
0.00
0.00
24-Oct-2026
25-Oct-2026