Project Completion Certificate (Ground Water)
Scheme ID: 20057837 Name of Scheme: BEHTA GOKUL JJM No. of Villages: 1 No. of Habitation Covered: 3
Total Population Covered: 7490 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 26-Aug-2024 Actual Date of Completion (Capex): 27-Apr-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 27M/115M BEHTA GOKUL 27.527339 80.003749
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE PUMP 87M³/47M BEHTA GOKUL 27.527339 80.003749
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 425KL/18M BEHTA GOKUL 27.527339 80.003749
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI PIPE 200 0.051
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE PN:-6 63 3.455
2 HDPE PIPE PN:-6 75 4.101
3 HDPE PIPE PN:-6 90 2.417
4 HDPE PIPE PN:-6 110 0.753
5 HDPE PIPE PN:-6 125 0.137
6 HDPE PIPE PN:-6 140 2.221
7 HDPE PIPE PN:-6 160 0.043
8 HDPE PIPE PN:-6 180 0.00
9 HDPE PIPE PN:-6 200 2.006
HSC Connection
Sno. Total Nos.
1 1530
Other Details
4.34
0.00
4.84
26-Jul-2025
25-Sep-2025