Project Completion Certificate (Ground Water)
Scheme ID: 20058136 Name of Scheme: BANSA JJM No. of Villages: 1 No. of Habitation Covered: 6
Total Population Covered: 5870 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 26-Feb-2024 Actual Date of Completion (Capex): 10-May-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 21.5 M/ 66.8 M BANSA 27.081508 80.211442
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 1.170 M³ per Min /43 Mtr BANSA 27.081508 80.211442
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 350 KL/ 14 Mtr BANSA 27.081601 80.211405
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 D.I. Pipe 200 0.023
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6: Class PE-100 63 4.4318
2 HDPE Pipe PN-6: Class PE-100 75 7.1333
3 HDPE Pipe PN-6: Class PE-100 90 5.6217
4 HDPE Pipe PN-6: Class PE-100 110 2.9708
5 HDPE Pipe PN-6: Class PE-100 125 0.292
6 HDPE Pipe PN-6: Class PE-100 160 0.2009
7 HDPE Pipe PN-6: Class PE-100 200 0.4684
HSC Connection
Sno. Total Nos.
1 1102
Other Details
3.83
0.00
3.85
09-Aug-2024
23-Sep-2026