Project Completion Certificate (Ground Water)
Scheme ID: 20058991 Name of Scheme: BIJGAWAN JJM No. of Villages: 2 No. of Habitation Covered: 2
Total Population Covered: 4720 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 10-Sep-2024 Actual Date of Completion (Capex): 18-Apr-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 27M/121M BIJGAWAN 27.552004 80.094858
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE PUMP 59.4M³/47M BIJGAWAN 27.552004 80.094858
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 300KL/18M BIJGAWAN 27.552004 80.094858
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI PIPE 200 0.045
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE PN:-6 63 3.187
2 HDPE PIPE PN:-6 75 2.38
3 HDPE PIPE PN:-6 90 1.307
4 HDPE PIPE PN:-6 110 3.012
5 HDPE PIPE PN:-6 125 0.149
6 HDPE PIPE PN:-6 140 0.348
7 HDPE PIPE PN:-6 160 0.00
8 HDPE PIPE PN:-6 180 0.564
9 HDPE PIPE PN:-6 200 2.962
HSC Connection
Sno. Total Nos.
1 930
Other Details
3.48
0.00
3.66
17-Jul-2025
25-Sep-2025